35 Ill. Adm. Code 742.900
Tier 3 Evaluation Overview
Section 742
Section 742.900Â Tier 3
Evaluation Overview
a)Â Â Â Â Â Â Â Â Tier 3 sets forth a flexible framework to develop remediation
objectives outside of the requirements of Tiers 1 and 2. Although Tier 1 and
Tier 2 evaluations are not prerequisites to conduct Tier 3 evaluations, data
from Tier 1 and Tier 2 can assist in developing remediation objectives under a
Tier 3 evaluation.
b)Â Â Â Â Â Â Â Â The level of detail required to adequately characterize a site
depends on the particular use of Tier 3. Tier 3 can require additional
investigative efforts beyond those described in Tier 2 to characterize the
physical setting of the site. However, in situations where remedial efforts
have simply reached a physical obstruction additional investigation may not be
necessary for a Tier 3 submittal.
c)Â Â Â Â Â Â Â Â Situations that can be considered for a Tier 3 evaluation
include, but are not limited to:
1)Â Â Â Â Â Â Â Â Modification of parameters not allowed under Tier 2;
2)Â Â Â Â Â Â Â Â Use of models different from those used in Tier 2;
3)Â Â Â Â Â Â Â Â Use of additional site data, such as results of indoor air
sampling, to improve or confirm predictions of exposed receptors to
contaminants of concern;
4)Â Â Â Â Â Â Â Â Analysis of site-specific risks using formal risk assessment,
probabilistic data analysis, and sophisticated fate and transport models (e.g.,
requesting a target hazard quotient greater than 1 or a target cancer risk
greater than 1 in 1,000,000);
5)Â Â Â Â Â Â Â Â Requests for site-specific remediation objectives because an
assessment indicates further remediation is not practical;
6)Â Â Â Â Â Â Â Â Incomplete human exposure pathways not excluded under Subpart
C;
7)Â Â Â Â Â Â Â Â Use of toxicological-specific information not available from
the sources listed in Tier 2;
8)Â Â Â Â Â Â Â Â Land uses which are substantially different from the assumed
residential or industrial/commercial property uses of a site (e.g., a site will
be used for recreation in the future and cannot be evaluated in Tier 1 or 2);
9)Â Â Â Â Â Â Â Â Requests for site-specific remediation objectives that exceed
Tier 1 groundwater remediation objectives so long as the following is
demonstrated:
A)
To the extent practical, the exceedance of the groundwater
quality standard has been minimized and beneficial use appropriate to the
groundwater that was impacted has been returned; and
B)
Any threat to human health or the environment has been
minimized
[415 ILCS 5/58.5(d)(4)(A)]; and
10)Â Â Â Â Â Â Â Â Use
of building control technologies, other than those described in Subpart L, to
prevent completion of the indoor inhalation exposure route.
d)Â Â Â Â Â Â Â Â For requests of a target cancer risk ranging between 1 in
1,000,000 and 1 in 10,000 at the point of human exposure or a target hazard
quotient greater than 1 at the point of human exposure, the requirements of
Section 742.915 shall be followed. Requests for a target cancer risk exceeding
1 in 10,000 at the point of human exposure are not allowed.
e)Â Â Â Â Â Â Â Â Requests for approval of a Tier 3 evaluation must be submitted
to the Agency for review under the specific program under which remediation is
performed. When reviewing a submittal under Tier 3, the Agency shall consider
whether
the interpretations and conclusions reached are supported by the information
gathered
[415 ILCS 58.7(e)(1)]. The Agency shall approve a Tier 3
evaluation if the person submits the information required under this Part and
establishes through such information that public health is protected and that
specified risks to human health and the environment have been minimized.
f)Â Â Â Â Â Â Â Â If contaminants of concern include polychlorinated biphenyls
(PCBs), requests for approval of a Tier 3 evaluation must additionally address
the applicability of 40 CFR 761.