35 Ill. Adm. Code 816.520
Poz-O-Tec Monofills
Section 816
Section 816.520Â Poz-O-Tec
Monofills
Any monofill receiving solely
FGD sludges and coal combustion wastes produced by coal combustion power
generating facilities shall be exempt from the requirements of 35 Ill. Adm.
Code 811.105 (solely as it relates to the placement of wastes at the lowest
part of the active face), 811.306, 811.307, 811.308, 811.309, 811.313 (solely
as it relates to soil cover), 811.314(b)(3)(C) (solely to the extent that it
may preclude Poz-O-Tec materials from being used as a landfill cap) and 811.321
(relating solely to waste placement), provided that:
a)Â Â Â Â Â Â Â Â The FGD sludges and coal combustion wastes have been processed
into Poz-O-Tec materials;
b)Â Â Â Â Â Â Â Â The permeability of the liner constructed of Poz-O-Tec
material is demonstrated to be less than or equal to 1 x 10
-7
cm/sec
after placement and curing based upon a geometric average of those cylinders
tested for permeability which were formed from a single sample in accordance
with Section 816.530(b);
c)Â Â Â Â Â Â Â Â The Poz-O-Tec material has an unconfined compressive strength
of greater than or equal to 150 psi using an arithmetic average of the strength
testing results obtained in accordance with Section 816.530;
d)Â Â Â Â Â Â Â Â The base of the monofill is constructed at least five feet
above the average historical groundwater table;
e)Â Â Â Â Â Â Â Â A monofill liner and low permeability cap is constructed from
the Poz-O-Tec materials as described in Section 816.510;
f)Â Â Â Â Â Â Â Â A drainage layer is constructed atop the monofill liner which
has a permeability greater than or equal to 1 x 10
-3
cm/sec which
extends over the entire liner system of the monofill;
g)Â Â Â Â Â Â Â Â The material is placed in such a manner that it will form a
monolithic block through placement of the material in one to two foot lifts,
which are compacted, rolled to smooth and graded and sloped such that any
rainfall rapidly runs off the upper surface without puddling;
h)Â Â Â Â Â Â Â Â At all times a berm is maintained around three sides of the
landfill mass and the grading is such that the run-off is directed toward the
open side where it is collected for reuse or treated (if necessary) and
discharged pursuant to an NPDES permit;
i)Â Â Â Â Â Â Â Â Â The material testing procedures specified in Section 816.530
are implemented;
j)Â Â Â Â Â Â Â Â Â Construction of the full scale monofill may commence
immediately upon completion of the test pad;
k)Â Â Â Â Â Â Â Â An acceptable groundwater impact assessment pursuant to 35
Ill. Adm. Code 811.371(b), 812.316, 813.304, or 815.203, as appropriate for the
given facility, is prepared; and
l)Â Â Â Â Â Â Â Â Â Owners or operators using the Poz-O-Tec materials in
accordance with this Section shall comply with the Illinois Environmental
Protection Act [415 ILCS 5] and 35 Ill. Adm. Code 811, to the extent those
provisions are not otherwise addressed herein.