35 Ill. Adm. Code 845.440
Hazard Potential Classification Assessment
Section
845.440 Hazard Potential Classification Assessment
a)
Hazard Potential Classification Assessments
1) The
owner or operator of the CCR surface impoundment must conduct an initial and
annual hazard potential classification assessment of the CCR surface
impoundment. The owner or operator must document the hazard potential
classification of each CCR surface impoundment as either a Class 1 or Class 2
CCR surface impoundment. The owner or operator must also document the basis
for each hazard potential classification.
2) The owner or operator of the CCR surface
impoundment must obtain a
certification from a
qualified professional engineer stating that the initial hazard potential
classification and each annual classification was conducted in accordance with
the requirements of this Section.
3) Timeframe for Submission of the
Hazard Potential Classification Assessment
s and
Certifications
A) The
owner or operator of a new CCR surface impoundment must submit the initial
hazard potential classification assessment certification with the initial
operating permit application before the initial receipt of CCR in the surface
impoundment.
B) The
owner or operator of an existing CCR surface impoundment must submit the
initial hazard potential classification assessment certification with its first
annual inspection report required by Section 845.540(b).
C) The owner or operator of a CCR surface
impoundment must submit the annual hazard potential classification assessment
certification each year with the annual inspection required by Section 845.540
(b).
D) The
owner or operator of a CCR surface impoundment must place each hazard potential
classification assessment in the facility's operating record (see Section
845.800(d)(4)).
b) The
requirements of this Section apply to all CCR surface impoundments, except for
those CCR surface impoundments that are incised CCR surface impoundments. If
an incised CCR surface impoundment is subsequently modified (e.g., a dike is
constructed) such that the CCR surface impoundment no longer meets the
definition of an incised CCR surface impoundment, the CCR surface impoundment
is subject to the requirements of this Section.