35 Ill. Adm. Code 845.510
Hydrologic and Hydraulic Capacity Requirements for CCR Surface Impoundments
Section 845.510 Hydrologic and Hydraulic Capacity
Requirements for CCR Surface
Impoundments
a) The
owner or operator of an existing or new CCR surface impoundment or any lateral
expansion of a CCR surface impoundment must design, construct, operate, and
maintain an inflow design flood control system as specified in subsections
(a)(1) and (2).
1) The
inflow design flood control system must adequately manage flow into the CCR
surface impoundment during and following the peak discharge of the inflow
design flood specified in subsection (a)(3).
2) The
inflow design flood control system must adequately manage flow from the CCR
surface impoundment to collect and control the peak discharge resulting from
the inflow design flood specified in subsection (a)(3).
3) The
inflow design flood, at a minimum, is:
A) For a
Class 1 CCR surface impoundment, as determined under Section 845.440(a), the
probable maximum flood;
B) For a
Class 2 CCR surface impoundment, as determined under Section 845.440(a), the
1000-year flood; or
C) For an
incised CCR surface impoundment, the 25-year flood.
b) Discharge
from the CCR surface impoundment must be handled in accordance with the surface
water requirements in Section 845.110(b)(3) and 35 Ill. Adm. Code Subtitle C.
c)
Inflow
Design Flood Control System Plan
1) Content
of the Plan. The owner or operator must prepare
initial
and annual inflow design flood control system plans
for the CCR surface
impoundment. These plans must document how the inflow design flood control
system has been designed and constructed to meet the requirements of this
Section. Each plan must be supported by appropriate engineering calculations.
2) Amendment
of the Plan. The owner or operator of the CCR surface impoundment may amend
the written inflow design flood control system plan at any time. The owner or
operator must amend the written inflow design flood control system plan
whenever there is a change in conditions that would substantially affect the
written plan in effect.
3) The owner
or operator must obtain a certification from a qualified professional engineer
stating that the initial and periodic inflow design flood control system plans
meet the requirements of this Section.
4) Timeframe for Plan Submission
A) The
owner or operator of a new CCR surface impoundment must submit to the Agency
the initial inflow design flood control system plan certification with the
initial operating permit application before the initial receipt of CCR in the
surface impoundment.
B) The
owner or operator of an existing CCR surface impoundment must submit the
initial inflow design flood control system plan certification with its first
annual inspection report required by Section 845.540(b).
C) The
owner or operator of a CCR surface impoundment must submit the annual inflow
design flood control system plan certification each year with the annual
inspection required by Section 845.540(b).
D) The
owner or operator of a new CCR surface impoundment must place each inflow
design flood control system plan in the facility's operating record (see
Section 845.800(d)(8)).