35 Ill. Adm. Code 845.540
Inspection Requirements for CCR Surface Impoundments
Section
845.540 Inspection Requirements for CCR Surface
Impoundments
a) Inspections by a Qualified
Person
1) All
CCR surface impoundments and any lateral expansion of a CCR surface impoundment
must be examined by a qualified person as follows:
A) At
intervals not exceeding seven days and after each 25-year, 24-hour storm,
inspect for the following:
i) Any
appearances of actual or potential structural weakness and other conditions that
are disrupting, or have the potential to disrupt, the operation or safety of
the CCR surface impoundment;
ii) Deterioration,
malfunctions or improper operation of overtopping control systems, where
present;
iii) Sudden
drops in the level of the CCR surface impoundment's contents;
iv) Erosion
that creates rills, gullies, or crevices six inches or deeper, other signs of
deterioration including failed or eroded vegetation in excess of 100 square
feet, or cracks in dikes or other containment devices; and
v) Any
visible releases;
B) At
intervals not exceeding seven days, inspect the discharge of all outlets of
hydraulic structures that pass underneath the base of the CCR surface
impoundment or through the dike, of the CCR surface impoundment, for abnormal
discoloration, flow or discharge of debris or sediment; and
C) At
intervals not exceeding 30 days, monitor all CCR surface impoundment
instrumentation.
2) The
owner or operator must prepare a report for each inspection that includes the
date of the inspection, condition of the CCR surface impoundment, any repairs
made to the CCR surface impoundment, and the date of the repair. The results of
the inspection by a qualified person must be recorded in the facility's
operating record as required by Section 845.800(d)(13).
3) The
owner or operator of a CCR surface impoundment must initiate the inspections
required by subsection (a) by April 30, 2021, or by initial receipt of CCR in a
CCR surface impoundment if the owner or operator becomes subject to this Part
after April 30, 2021. The inspections required by subsection (a) must continue
until the completion of closure by removal or the completion of post-closure
care.
4) If a
25-year, 24-hour storm is identified more than 48 hours before the next
scheduled weekly inspection, an additional inspection must be conducted within
24 hours after the end of the identified storm event, before the scheduled
seven-day inspection.
b) Annual
Inspections By a Qualified Professional Engineer
1) The
CCR surface impoundment must be inspected on an annual basis by a qualified
professional engineer to ensure that the design, construction, operation, and
maintenance of the CCR surface impoundment is consistent with recognized and
generally accepted engineering standards. The inspection must, at a minimum,
include:
A) A
review of available information regarding the status and condition of the CCR
surface impoundment, including files available in the operating record (e.g.,
CCR surface impoundment design and construction information required by
Sections 845.220(a)(1) and 845.230(d)(2)(A), previous structural stability
assessments required under Section 845.450, the results of inspections by a
qualified person, and results of previous annual inspections);
B) A
visual inspection of the CCR surface impoundment to identify signs of distress
or malfunction of the CCR surface impoundment and appurtenant structures;
C) A
visual inspection of any hydraulic structures underlying the base of the CCR
surface impoundment or passing through the dike of the CCR surface impoundment
for structural integrity and continued safe and reliable operation;
D) The
annual hazard potential classification certification, if applicable (see
Section 845.440);
E) The
annual structural stability assessment certification, if applicable (see
Section 845.450);
F) The
annual safety factor assessment certification, if applicable (see Section
845.460); and
G) The
inflow design flood control system plan certification (see Section 845.510(c)).
2)
Inspection Report
. The qualified professional engineer
must prepare a report following each inspection that addresses the following:
A) Any
changes in geometry of the impounding structure since the previous annual
inspection;
B) The
location and type of existing instrumentation and the maximum recorded readings
of each instrument since the previous annual inspection;
C) The
approximate minimum, maximum, and present depth and elevation of the impounded
water and CCR since the previous annual inspection;
D) The
storage capacity of the impounding structure at the time of the inspection;
E) The
approximate volume of the impounded water and CCR at the time of the inspection;
F) Any
appearances of an actual or potential structural weakness of the CCR surface
impoundment, in addition to any existing conditions that are disrupting or have
the potential to disrupt the operation and safety of the CCR surface
impoundment and appurtenant structures; and
G) Any
other changes that may have affected the stability or operation of the
impounding structure since the previous annual inspection.
3) By
January 31 of each year, the inspection report must be completed and included
with the annual consolidated report required by Section 845.550.
4) Frequency
of Inspections. The owner or operator of the CCR surface impoundment must
conduct the inspection required by subsections (b)(1) and (2) on an annual
basis. The deadline for conducting a subsequent inspection is based on the
date of conducting the previous inspection.
5) If a
deficiency or release is identified during an inspection, the owner or operator
must
submit
to the Agency documentation detailing proposed corrective measures and obtain
any necessary permits from the Agency.