44 Ill. Adm. Code 8.3095
Phase 1 Design-Build Evaluation
Section 8.3095Â Phase 1 Design-Build Evaluation
a)Â Â Â Â Â Â Â Â In Phase 1, CDB will evaluate and shortlist the
DB entities based on qualifications submitted in response to the RFP.
b)Â Â Â Â Â Â Â Â Evaluation shall be based on the
prequalification requirements, evaluation criteria and relative importance or
weighting of evaluation criteria as set forth in the RFP.
c)Â Â Â Â Â Â Â Â Proposals
shall not be reviewed until after the deadline for submission has passed.
d)Â Â Â Â Â Â Â Â Proposals must meet all material requirements of
the RFP or they may be rejected as non-responsive.
e)Â Â Â Â Â Â Â Â CDB
shall have the right to reject any and all proposals subject to CPO approval.
f)Â Â Â Â Â Â Â Â CDB shall maintain a record of the evaluation
scoring to be disclosed in event of a protest regarding the solicitation.
g)Â Â Â Â Â Â Â Â Phase
1 evaluation criteria shall include:
1)Â Â Â Â Â Â Â Â experience
of personnel;
2)Â Â Â Â Â Â Â Â successful
experience with similar project types;
3)Â Â Â Â Â Â Â Â financial
capability in relation to the size of the project;
4)Â Â Â Â Â Â Â Â timeliness
of past performance;
5)Â Â Â Â Â Â Â Â experience
with similarly sized projects;
6)Â Â Â Â Â Â Â Â successful
reference checks of the firm;
7)Â Â Â Â Â Â Â Â commitment
to assign personnel for the duration of the project;
8)Â Â Â Â Â Â Â Â qualifications
of the entity's design consultants;
9)Â Â Â Â Â Â Â Â CDB prequalification in good standing of any
subcontractor proposed to perform any of the 5 subdivisions of work defined in
Section 30-30 of the Code;
10)Â Â Â Â Â Â Â Â Ability or past performance in meeting or
exhausting good faith efforts to meet the utilization goals for business
enterprises established in the BEMFD Act, Section 45-57 of the Code and with
Section 2-105 of the Illinois Human Rights Act;
11)Â Â Â Â Â Â Â Â Other relevant criteria deemed necessary by
CDB.
h)Â Â Â Â Â Â Â Â CDB will eliminate any DB entity from
consideration for evaluation or award if the entity has any pecuniary interest
in the project or has other relationships or circumstances, including, but not
limited to, long-term leasehold, mutual performance, or development contracts
with CDB, that may give the DB entity a financial or tangible advantage over
other DB entities in the preparation, evaluation or performance of the DB
contract or that create the appearance of impropriety.
i)Â Â Â Â Â Â Â Â Â CDB will not consider any proposal that does
not include the entity's plan to comply with the requirements established in
the BEMFD Act and with Section 2-105 of the Illinois Human Rights Act, if
applicable.
j)Â Â Â Â Â Â Â Â Â CDB will publish the names of all DB entities
submitting Phase 1 proposals on CDB's volume of the Procurement Bulletin and in
the next Professional Services Bulletin (within the CDB volume of the
Procurement Bulletin) after the deadline for submission.