14 Ill. Adm. Code 521.100
Certificate of Exemption or Verification
Section 521.100 Certificate of Exemption or Verification
a) Department-Qualifying
Data Center MOU
Upon receipt of a fully-executed MOU
between the qualifying data center and the Department, the Department will
issue to the qualifying data center a certificate of exemption demonstrating
that the qualifying data center's qualifying purchases are exempt from the
taxes, as set forth in Section 605-1025(a).
b) Qualifying
Data Center-Tenant MOU
Upon receipt of a fully-executed MOU
between the qualifying data center and its tenant and acknowledged by the
Department (or Tenant Participation Certificate Memorandum of Understanding, a
form of which is included with the MOU between the Department and the data
center owner or operator) as referenced in Section 90(b), the Department will
issue to the data center tenant a certificate of exemption demonstrating that
the data center tenant's qualifying purchases are exempt from the taxes, as set
forth in Section 605-1025(a) of the Statute.
c) A
qualifying data center located in an underserved area, as certified by the
Department,
for taxable years beginning on or after January 1, 2019,
shall be awarded
credits against the taxes imposed under Section 201(a) and
(b) of the Illinois Income Tax Act, as provided in Section 229 of that Act.
[20 ILCS 605/605-1025(d)]
1) The
qualifying data center shall notify the Department, on forms provided by the
Department, at the end of the taxable year for which a credit is sought, the
wages
paid during the taxable year to a full-time or part-time employee of a
construction contractor employed by a certified data center, if those wages are
paid for the construction of a new data center in
an underserved area
;
2) Upon
receipt of valid proof from the qualifying data center, the Department will
provide a certificate of verification equal to
20% of the wages paid during
the taxable year to a full-time or part-time employee of a construction
contractor employed by a certified data center if those wages are paid for the
construction of a new data center in
an underserved area
. [35 ILCS
5/229(a)]