56 Ill. Adm. Code 6000.353
Trampoline Courts
Section 6000.353 Trampoline Courts
a) This
Section shall govern all trampoline courts (courts) in operation on or after
January 1, 2022. Courts subject to the Act must comply with the inspection and
permitting requirements of this Part by February 1, 2022.
b) Trampoline
courts must comply with ASTM 2970-20.
c) In
addition to the definitions in Section 2-2 of the Act and Section 6000.10, the
following shall apply to and govern this Section 6000.353:
"Commissioning" means an
action by the installer or other competent person of putting a new element or
court into service for the owner or operator.
"Competent Person" means
a person possessing the skills, knowledge, experience, training, and judgment
to perform assigned tasks or activities satisfactorily, as determined by a
reasonable person.
"Major Modification"
means a change in either the structural or operational characteristics of an
amusement ride or amusement attraction that can alter its performance from that
specified in the manufacturer’s design criteria.
"Operating System" means
the system or systems of processing a patron through the court.
"Operating Manual" means
a document containing the procedures and forms for the operation of the court
activity and equipment on the site.
"Third-Party
Inspector" means a qualified person not directly employed by the operator
of the court or parent company, original equipment manufacturer (OEM), or
vendor, and not offering other services to the operator of the court or parent
company, who is qualified via International Association of Trampoline Parks
accreditation, NAARSO certification, or other equivalent certification to
provide court inspections, as determined by the Department.
d) This
Section specifies the site, site approval, design, testing of equipment,
management of the operation, operating procedures, and emergency provisions and
procedures for courts. All courts shall meet the manufacturer's standards and
specifications.
e) Site
Plan and Equipment Design and Construction
1) This
Section (e) shall apply to courts undergoing a major modification or newly
constructed after January 1, 2022. All court operating system design documents
shall be reviewed and sealed by a licensed professional engineer
. ASTM 2970-20 and
other applicable standards shall be
used as general guidance. The designer of the court is responsible for
preparing the design report for the owner. The design report shall contain site
plans, safety zones, drawings, a design evaluation, and specifications for
equipment, platform, rigging system, and safety equipment. The design report
shall be submitted to the Department before the commissioning of the court and
shall be maintained on-site. The design evaluation included in the report shall
consider the following:
A) Static
and dynamic loads on anchors and components.
B) Fatigue
limits or absolute component replacement intervals.
C) Fatigue
limits for structures.
D) Protection
against metallic corrosion.
E) Clearances
and hazard analysis.
F) Platform,
walkway, ladder and associated foundation size and load ratings, including
factors of safety.
2) An
inspection by a third-party inspector shall be conducted each time a major design
component is modified. Scheduled component replacements in accordance with
manufacturer or designer maintenance procedures do not constitute a design
modification.
3) Courts
shall be inspected by a third-party inspector annually. The information
gathered from the inspection shall be presented in a report to the owner in
accordance with the ASTM 2970-20 and industry standards or equivalent standards
as approved by the Department. The inspection report shall be submitted to the
Department at the time the application for a permit is submitted to the
Department.
4) Differences
between the design as detailed in the engineer's report and evaluation and the
implemented installation by a competent person shall be reconciled. Appropriate
explanations of the differences, which may include modified drawings,
procedures, analyses, and additional calculations, shall be appended to the
original design report or engineering evaluation as applicable. Owner's manuals
shall be updated to reflect the engineer's or manufacturer's acceptance of the
modifications.
5) A
court commissioning plan, including an acceptance test procedure and report,
shall be incorporated in the engineer's report. Commissioning and testing shall
be conducted by a competent person.
6) Any
materials or data made available to or received by any agent or employee of the
Department that contains information that is exempt from disclosure under
Section 7 of the Freedom of Information Act [5 ILCS 140/7] shall not be
disclosed.
f) General
Compliance Criteria
1) Equipment
A) There
shall be adequate clear space above, below, and around the court to ensure
participants will not strike or contact any permanent object.
B) Equipment
appropriate for applicable rescue, rescue plans, and personnel trained to
retrieve a participant from anywhere within the court shall be present during
court operation.
C) All
parts and components shall be purchased from the manufacturer or shall only be
manufacturer-approved replacement parts. If the manufacturer is no longer in
business, replacement parts shall be procured in a manner consistent with ASTM
2970-20.
D) Performance
trampolines, as the term is used in ASTM F2970-20, shall not be allowed for
public use in any regulated trampoline court.
2) Court
Protection
Courts shall have appropriate
safety devices, such as impact-absorbing materials, landing mats, or nets,
installed per the manufacturer's design specifications and ASTM 2970-20. Descriptions
and operating characteristics of the safety devices shall be included in the
design drawings.
g) Site
Operating Manual and Documentation
1) Each
court shall have an operating manual for the safe operation of court activities
on-site. The operating manual and all amendments shall be on-site and freely
available to operating staff and governing bodies.
2) The
operating manual shall include the procedures that will be used by the court to
comply with this Part.
3) The
operating manual shall include, but not be limited to, the following:
A) A site
plan.
B) A
description of operating systems and equipment.
C) Job
procedures, including training, for each task in the operating system. The
staff training plan shall include documentation of training provided by a
qualified industry training professional, including certificates verifying
competency.
i) Court
managers shall be 21 years of age or older and shall hold a current Red Cross
first aid certificate and a current Red Cross cardiopulmonary resuscitation
(CPR) certificate, or their equivalent. At least one court manager must be
present on-site at all times during court operation.
ii) Operating
staff shall have complete knowledge of the operation of the court.
iii) At
no time shall the ratio of participants to attendants and assistants exceed
32:1.
D) Job
descriptions.
E) Sample
of staff qualifications.
F) Staff
selection procedures.
G) Maintenance
standards and procedures.
H) Testing
procedures and recording.
I) Criteria
for the periodic equipment replacement.
J) Emergency
plan.
K) Reporting
of injuries, damage, and incidents.
L) Requirements
for maintaining logs, including:
i) Site
ii) Equipment
iii) Personnel
M) Records
to be kept.
N) Inspection
procedures, standards, and follow-up actions.
O) Examples
of forms to be used.
h) Emergency
Plan and Provisions
1) Each
court shall have an emergency plan, including appropriate procedures to be
followed in case of emergency, that has been reviewed with the local police and
fire departments by court management, and must maintain documentation that such
review took place, including any recommendations provided by the police or fire
department.
2) Each
court shall have a medium first aid kit and blankets on site.
i) If a
court meets all the equipment and inspection requirements of this Part, the
Department shall issue an operating permit, subject to the applicant submitting
the fees for Amusement Attractions required by Section 6000.50(a)(3) and
(b)(3).
j) An
owner or operator of a court that is permitted under the requirements of the
Act and this Part may disclose or advertise such permit status. Misrepresentation
of permit status shall be a violation of the Act. No owner or operator shall
advertise any court as being otherwise endorsed or approved by the Department,
in any advertisement, brochure, commercial, TV or radio show, or newspaper, or
in any other public manner.