77 Ill. Adm. Code 11300.1130.730
Extension of the Financial Commitment Period
Section 1130
TITLE 77: PUBLIC HEALTH
CHAPTER II: HEALTH FACILITIES AND SERVICES REVIEW BOARD
SUBCHAPTER b: OTHER BOARD RULES
PART 1130 HEALTH FACILITIES AND SERVICES REVIEW OPERATIONAL RULES
SECTION 1130.730 EXTENSION OF THE FINANCIAL COMMITMENT PERIOD
Section 1130.730 Extension
of the Financial Commitment Period
a) HFSRB may grant the permit holder a single extension to
financially commit at least 33% of the total project costs. An extension shall
be for a period of up to one year from the previously established financial
commitment date.
b) The permit holder shall submit a request for extension in
writing or by electronic means to dph.hfsrb@illinois.gov, along with an
application-processing fee (see Section 1130.230(i)(4)(A)).
c) A
request for extension must be received by the Administrator at least 45 days
prior to the established financial commitment date.
d) A
request for an extension that is received less than 45 days prior to the
established financial commitment date shall be accepted by the Administrator
but an additional processing fee will be assessed (see Section
1130.230(i)(4)(B)).
e) Any
fee paid for a financial extension request is in addition to the initial
application fee referenced in Section 1130.230(i)(2)(C).
f) HFSRB review of a financial extension request shall not
commence until the required fee has been submitted.
g) Extension
requests that are received after the established financial commitment date
shall also be subject to the fines provided in Section 14.1 of the Act and
Section 1130.790.
h) HFSRB Staff Review
1) HFSRB staff shall review the financial extension request and
prepare a report of its findings.
2) If the financial extension request is in conformance with all
applicable HFSRB criteria (see Section 1130.730) and the HFSRB staff's findings
are positive, the request and related documentation shall be sent to the
Chairman. If the Chairman is unavailable, the application and related
documentation will be sent to the Vice Chairman.
3) If the request is not in conformance with all applicable HFSRB
criteria or the HFSRB staff's findings are not positive, the request and
related documentation shall be sent to the HFSRB.
i) HFSRB
Chairman Review and Consideration
1) After
receipt of the extension request, the Chairman shall:
A) approve
the request; or
B) deny
the request; or
C) refer the request to
HFSRB for consideration.
2) HFSRB
staff shall provide electronic correspondence to the permit holder of the
Chairman's determination through dph.hfsrb@illinois.gov.
j) HFSRB
Review and Consideration
1) Projects
that continue to comply with the provisions of 77 Ill. Adm. Code 1110 and 1120
and that have shown good cause by submitting the required information for an
extension request specified in subsection (b), and for which the causes for
delays are beyond the permit holder's control, shall be approved for extension.
2) If an
extension request is referred to the HFSRB, it shall be scheduled for the HFSRB
meeting that is at least 10 days from the date the request was referred to the
HFSRB.
3) After
receipt of the extension request, HFSRB shall:
A) approve
the request; or
B) deny
the request.
4) HFSRB
staff shall provide electronic correspondence to the permit holder of HFSRB's
determination through dph.hfsrb@illinois.gov.
k) If
the extension request is denied (either by the Chairman or HFSRB), the permit
holder shall be afforded an opportunity for reconsideration through HFSRB's
Declaratory Ruling process (see Section 1130.810).
l) Denial
of an extension request by HFSRB shall constitute the final HFSRB decision and
is not subject to administrative appeal.