77 Ill. Adm. Code 250.2420
Submission of Plans for New Construction, Alterations or Additions to Existing Facility
Section 250
Section 250.2420Â Submission
of Plans for New Construction, Alterations or Additions to Existing Facility
a)Â Â Â Â Â Â Â Â New Construction, Addition or Major Alteration
1)Â Â Â Â Â Â Â Â For all construction of either new buildings or additions or
alterations to existing buildings coming within the scope of this Part, design
development drawings and outline specifications shall be submitted to the
Department for review. Approval of design development drawings and
specifications shall be obtained from the Department prior to starting final
working drawings and specifications. Comments or approval shall be provided
within 30 days after receipt by the Department.
2)Â Â Â Â Â Â Â Â Final Drawings
A)Â Â Â Â Â Â Â The final working drawings and specifications shall be
submitted to the Department for review and approval prior to the beginning of
construction. Alternative methods of design development and construction may be
acceptable subject to the approval of the Department. Department approval is
void if construction contracts are not executed and construction is not started
within one year after the plan approval date. Comments by the Department shall
be provided within 60 days after the day on which the submission is deemed
complete.
B)Â Â Â Â Â Â Â The Department shall be notified of the award of construction
contracts.
3)Â Â Â Â Â Â Â Â Any contract modifications that affect or change the function,
design, or purpose of a facility shall be submitted to the Department for
approval prior to proceeding with modifications. Comments or approval shall be
provided within 30 days after receipt by the Department.
4)
The Department
will
conduct an on-site inspection of
the completed project no later than 15 business days after notification from
the applicant that the project has been completed and all certifications
required by the Department have been received and accepted by the Department
.
The Department
may
extend this deadline only if a federally
mandated survey time frame takes precedence. Â The Department
will
provide
written approval for occupancy to the applicant within 5 working days
after
the Department's final inspection, provided the applicant has demonstrated
substantial compliance. Â Occupancy of new major construction is prohibited
until Department approval is received, unless the Department has not acted
within the time frames provided in
Section 8(g) of the Act and this
subsection (a)(4),
in which case the construction shall be deemed approved. Â Occupancy
will
be authorized after any required health inspection by the
Department has been conducted
. (Section 8(g) of the Act)
5)Â Â Â Â Â Â Â Â As-built drawings shall be maintained by the hospital. For the
purposes of this Section, "as-built drawings" are the original design
drawings revised to reflect any changes made in the field, including, but not
limited to, design changes issued by change order, component relocations
required for coordination, or rerouting of distribution systems.
b)Â Â Â Â Â Â Â Â Minor Alterations and Remodeling. Minor alterations or
remodeling changes that do not affect the structural integrity of the building,
that do not change functional operation, that do not affect fire safety, and
that do not add beds or facilities over those for which the hospital is
licensed do not need to be submitted for approval.
c)Â Â Â Â Â Â Â Â Alterations of Water Supply, Plumbing and Drainage. No system
of water supply, plumbing, sewage, garbage or refuse disposal shall be
installed, nor shall any existing system be altered or extended, until complete
plans and specifications for the installation, alteration or extension have
been submitted to the Department and have been reviewed and approved.
d)Â Â Â Â Â Â Â Â Codes and Standards
1)Â Â Â Â Â Â Â Â Nothing in this Part shall relieve the sponsor from compliance
with building codes, ordinances, and regulations that are enforced by city or
county jurisdictions.
2)Â Â Â Â Â Â Â Â The recommendations of the International Building Code shall
apply insofar as the recommendations are not in conflict with this Part or with
the NFPA 101. For construction of new buildings or additions, renovations, or
alterations to existing buildings coming within the scope of this Part in
municipalities with no building code of their own, the hospital may comply with
the International Building Code.
3)Â Â Â Â Â Â Â Â The codes and standards referenced in this Part may be ordered
from the various agencies at the addresses listed in Section 250.105 and are
effective on the dates cited in that Section.