77 Ill. Adm. Code 855.330
Operations and Maintenance
Section 855
Section 855.330Â Â Â Â Â Â Â Â Â Operations
and Maintenance
a)Â Â Â Â Â Â Â Â The school board or building owner shall designate a person
who shall be responsible for the implementation of an operations and
maintenance plan. The plan shall be instituted in every school identified or
assumed as having ACBM and shall be enforced at all times. The plan shall be
in writing and shall meet the requirements of USEPA (40 CFR 763) and OSHA
Regulations (29 CFR 1926.1101).
b)Â Â Â Â Â Â Â Â Repair Procedures. Department-licensed asbestos workers shall
be utilized when ACBM must be drilled, sanded, cut, or repaired, or friable
ACBM must be cleaned and the following procedures shall be followed:
1)Â Â Â Â Â Â Â Â Heating, cooling, or ventilating air systems shall be shut
down to prevent fiber dispersal to other areas of the building.
2)Â Â Â Â Â Â Â Â Openings in the work area, including windows, doorways, vents,
and any other openings, shall be sealed off with six mil polyethylene or
equivalent sheeting and duct tape.
3)Â Â Â Â Â Â Â Â All persons shall wear respirators equipped with high
efficiency HEPA filters and approved by the National Institute for Occupational
Safety and Health (NIOSH).
4)Â Â Â Â Â Â Â Â All persons shall wear disposable full body coveralls and head
gear.
5)Â Â Â Â Â Â Â Â ACBM shall be wet down with amended water before repairing or
disturbing the material to reduce airborne fiber release.
6)Â Â Â Â Â Â Â Â Work area shall be cleaned up using wet rags, mops or sponges,
leaving no visible residue.
7)Â Â Â Â Â Â Â Â Asbestos-contaminated waste shall be sealed in six mil labeled
plastic bags and disposed of at an approved disposal site.
8)Â Â Â Â Â Â Â Â Maintenance or repair which results in the disturbance of ACBM
shall be conducted in accordance with OSHA Regulations 29 CFR 2926.1101(e) and
(g).
c)Â Â Â Â Â Â Â Â The Floor Tile Project Notice form provided by the Department
must be submitted at least 10 working days prior to the beginning of an asbestos
resilient floor covering material project in a school building.