77 Ill. Adm. Code 855.350
Submissions and Notices
Section 855
Section 855.350Â Submissions
and Notices
a)Â Â Â Â Â Â Â Â The contractor shall submit the following items to the
Department postmarked or facsimile dated at least 10 working days prior to the
commencement of an asbestos abatement project.
1)Â Â Â Â Â Â Â Â The Notice of Asbestos Abatement Form provided by the
Department shall be completed and submitted by the contractor for all abatement
projects. The completed form shall contain only correct and accurate
information.
2)Â Â Â Â Â Â Â Â Written permission from the building owner confirming the
authorization for the commencement of abatement according to Section 855.450(g)
shall be attached to the notification form and submitted to the Department.
b)Â Â Â Â Â Â Â Â The contractor shall notify the Department in writing on the
form provided by the Department prior to any change in start date, completion
date and scope of the project.
c)Â Â Â Â Â Â Â Â Five days prior to commencement of work, the contractor shall
submit the following items to the project manager. These items shall be
up-to-date and shall be maintained at the abatement site by the project
manager.
1)Â Â Â Â Â Â Â Â Documentation of arrangements for the transport and disposal
of asbestos-containing or contaminated materials and supplies and the name and
location of the disposal site.
2)Â Â Â Â Â Â Â Â Documentation that each asbestos worker and supervisor are
licensed.
3)Â Â Â Â Â Â Â Â Drawings for layout and construction of decontamination
enclosure systems and barriers for isolation of the work area.
4)Â Â Â Â Â Â Â Â When rental equipment is to be used in removal areas or to
transport waste materials, a copy of the written notification to inform the
rental company of the nature of use of the rented equipment.
5)Â Â Â Â Â Â Â Â Results of materials testing as conducted before the abatement
for purposes of utilization during abatement activities (e.g., testing of
encapsulant for depth of penetration, testing of substitute materials for
adherence to encapsulated surfaces).
6)Â Â Â Â Â Â Â Â Copies of initial and current accreditation certificates of
all licensed persons and the original license. The project manager shall make
copies of all licenses at the location where they are conducting work. Failure
to have accreditation certificates at the job site could result in
decertification.
d)Â Â Â Â Â Â Â Â During abatement activities the contractor shall submit on a
weekly basis the following items to the project manager and the project manager
shall maintain this documentation at the abatement site:
1)Â Â Â Â Â Â Â Â Job progress reports detailing abatement activities, including
a review of progress with respect to previously established schedules, problems
and actions taken, injury reports, and equipment breakdowns.
2)Â Â Â Â Â Â Â Â Copies of all transport manifests, trip tickets and disposal
receipts for all asbestos waste materials removed from the work area during the
abatement process shall be submitted to the project manager within 10 days
after the completion of the project.
3)Â Â Â Â Â Â Â Â Copies of worksite entry log books with information on worker
and visitor access.
4)Â Â Â Â Â Â Â Â Logs documenting filter changes on respirators, HEPA vacuums,
negative pressure ventilation units, and other engineering controls.
5)Â Â Â Â Â Â Â Â Logs documenting that each asbestos worker present and in the
abatement area was licensed as such by the Department.
6)Â Â Â Â Â Â Â Â Any revisions to the start date, completion date or scope of
the project.
e)Â Â Â Â Â Â Â Â Prior to commencement of work the school board or the building
owner shall:
1)Â Â Â Â Â Â Â Â Notify occupants of work areas that may be disrupted by the
abatement project of dates and requirements for relocation. Arrangements must
be made prior to start of the project for relocation of desks, files, equipment
and personal possessions in order to avoid unauthorized access into the work
area by building occupants. Notification of all building occupants and users
is required in order to prevent unnecessary or unauthorized access to the
contaminated work area.
2)Â Â Â Â Â Â Â Â Submit to the contractor and project manager results of
background level air sampling, including sampling location, name of the air
sampling professional, equipment utilized and method of analysis. Background
air samples shall be collected and analyzed prior to the start of project
activities.
3)Â Â Â Â Â Â Â Â Provide to the contractor information concerning access,
shutdown, and protection requirements of equipment and systems in the work
area.
4)Â Â Â Â Â Â Â Â Submit to the contractor names and addresses of all asbestos
project managers and air sampling professionals assigned to the project prior
to the commencement of abatement. Any changes of the building owners'
representatives shall be submitted to the contractor in writing prior to such
change.
5)Â Â Â Â Â Â Â Â Provide to the contractor written permission authorizing the
commencement of asbestos abatement.
6)Â Â Â Â Â Â Â Â The school board or building owner shall provide the
contractor with written verification that notification of all building
occupants and users have been made pursuant to this Section prior to
commencement of the project. Such written verification shall be submitted to
the Department by the contractor with the Notice of Asbestos Abatement form
provided by the Department.