77 Ill. Adm. Code 855.440
Maintenance of Decontamination Enclosure Systems and Workplace Barriers
Section 855
Section 855.440Â Maintenance
of Decontamination Enclosure Systems and Workplace Barriers
a)Â Â Â Â Â Â Â Â Following completion of the construction of all polyethylene
barriers and decontamination system enclosures, the contractor, or his
designated representative, and project manager shall allow a minimum of six
hours settling time to ensure that barriers will remain intact and secured to
walls and fixtures before beginning actual abatement activities. The negative
air pressure equipment shall be in operation during this settling time.
b)Â Â Â Â Â Â Â Â All polyethylene barriers inside the work area, in the worker
decontamination enclosure system, and in the equipment decontamination
enclosure system, and partitions constructed to isolate the work area from
occupied areas, shall be inspected by the contractor and project manager at
least twice daily. The barriers shall be inspected before the start of and
following the completion of the day's abatement activities. Inspections and
observations shall be documented in all project log books.
c)Â Â Â Â Â Â Â Â Damage and defects in the enclosure system shall be repaired
upon discovery.
d)Â Â Â Â Â Â Â Â Smoke tubes shall be used by the contractor to test the
effectiveness of the work area barrier system before abatement work begins and
at least once a day thereafter until the work is completed. The project
manager shall observe the test. Results and observations shall be documented
in all project log books.
e)Â Â Â Â Â Â Â Â At any time during the abatement activities after barriers
have been erected, if visible emissions are observed outside of the work area
or if damage occurs to barriers, work shall stop, repairs shall be made to the
barriers, and visible residue cleaned up using appropriate HEPA vacuuming and
wet mopping procedures prior to resuming abatement activities.
f)Â Â Â Â Â Â Â Â The contractor shall HEPA vacuum or wet clean the equipment
decontamination enclosure system and the entire worker decontamination
enclosure system at the end of each day of abatement activities.
g)Â Â Â Â Â Â Â Â If air samples collected outside of the work area during
abatement activities indicate airborne fiber concentrations greater than
original background levels or 0.01 f/cc as determined by PCM, work shall stop
for inspection and repair of barriers. Cleanup of surfaces outside of the work
area using HEPA vacuums or wet cleaning techniques shall be done. Air sampling
shall indicate a fiber concentration less than background levels, or below 0.01
f/cc as determined by PCM, prior to resuming abatement activities. (See Section
855.340(b)(2)(B)(iii).)
h)Â Â Â Â Â Â Â Â Negative pressure ventilation equipment shall be installed and
operated to provide a minimum of four air changes in the work area every hour.Â
Openings made in the enclosure system to accommodate these units shall be made
airtight with tape and/or caulking. If more than one ventilation unit is
installed, units shall be turned on one at a time while checking the integrity
of wall barriers for secure attachment and the need for additional
reinforcement. A power supply shall be available to satisfy the requirements
of the ventilating units. Negative pressure ventilation units shall be
exhausted to the outside of the building away from occupied areas. Twelve inch
extension ducting shall be used to reach from the work area to the outside of
the building when ducting is required. Careful installation, air monitoring
and daily inspections by the contractor and project manager shall be done to
insure that the ducting does not release fibers into uncontaminated building
areas.
i)Â Â Â Â Â Â Â Â Â Once constructed and reinforced, and with negative pressure
ventilation units in operation, worker and equipment decontamination enclosures
shall be tested for leakage by the contractor, utilizing smoke tubes. The
project manager shall observe these tests. Enclosures shall be repaired or
reconstructed as needed. Results and observations shall be documented in all
project log books.
j)Â Â Â Â Â Â Â Â Â The contractor shall identify and maintain emergency and fire
exits from the work area.