77 Ill. Adm. Code 855.450
Commencement of Work
Section 855
Section 855.450Â Commencement
of Work
The contractor shall not begin
abatement work until the following requirements have been met:
a)Â Â Â Â Â Â Â Â Enclosure systems shall be constructed and tested.
b)Â Â Â Â Â Â Â Â All pre-abatement submissions, notifications, postings and
permits shall be provided and are satisfactory to the project manager.
c)Â Â Â Â Â Â Â Â All equipment for abatement, cleanup and disposal shall be on
hand.
d)Â Â Â Â Â Â Â Â All worker training and licensing shall be completed.
e)Â Â Â Â Â Â Â Â Arrangements shall be made for building security.
f)Â Â Â Â Â Â Â Â The number of clearance air samples and the specific sample
locations shall be established in conjunction with the air sampling
professional before abatement activity begins (see Section 855.470).
g)Â Â Â Â Â Â Â Â The contractor shall receive written permission from the
building owner to commence abatement. Such written permission shall be
submitted to the Department attached with the Notice of Asbestos Abatement Form
provided by the Department.
h)Â Â Â Â Â Â Â Â The building owner shall notify all parents, faculty and staff
of the pending abatement project and notify the contractor with written
verification of such notification. Such written verification shall be
submitted to the Department by the contractor attached to the Notice of
Asbestos Abatement Form provided by the Department.
i)Â Â Â Â Â Â Â Â Â The contractor shall be responsible for providing personal
protection for its employees according to the OSHA Construction Standard 29 CFR
1926.1101 (effective October 11, 1994).