77 Ill. Adm. Code 906.70
Distribution System (for sewage flows in excess of 800 gallons per day)
Section 906
Section 906.70 Distribution
System (for sewage flows in excess of 800 gallons per day)
a) Design criteria for laterals.
1) The variation in discharge rates from the perforations in any
lateral shall not exceed ten percent.
2) The variation in discharge rates between the perforations of
any two laterals shall not exceed 15%.
3) The pressure at the distal ends of the lateral shall be at
least 2.5 feet of water.
b) Perforations. The perforation requirements of this Section
shall be used in place of those of Section 906.60.
1) The perforations shall be spaced uniformly along the laterals
and at an interval not to exceed 10 feet.
2) Perforations shall be installed perpendicular to the
centerline of the lateral and along the lateral invert.
3) Perforation diameter shall be between ¼ and ⅝ inches.
4) To facilitate the draining of laterals between dosing cycles,
a perforation shall be installed at the distal end of each lateral near the
crown of the pipe.
c) Network Configuration
1) The laterals shall be installed in seepage beds. The lateral
spacing shall equal the perforation spacing. The perforations of adjacent laterals
in the bed shall be staggered.
2) Mounds employing multiple beds may be used. Also, multiple
mounds may be employed. If bed elevations are not all equal, then this fact
must be considered in the design of the pipe network in order to provide
uniform dosing of effluent.
3) Manifold-to-lateral connections shall be made using tee-to-tee
construction, with the manifold below the laterals (see Appendix A,
Illustration G). If the design is such that the manifold does not drain
between dosing cycles, then insulation or some other means shall be provided to
prevent freezing. In addition, provisions shall be made for manual draining of
the manifold.
4) Two separate distribution networks may be employed, with each
network receiving alternate doses of effluent through the use of alternating
pumps, valves, or siphons.
5) Siphons or siphon breaks shall be used in networks where the
low water level in the pumping chamber is above the lateral inverts.
d) Pumping Chamber
1) Dosing volume. Dosing volume shall be determined by dividing
the average daily sewage flow by the dosing frequency for the particular soil
type, as is shown in Appendix A, Illustration H. Dosing volume shall be at
least five times the pipe volume of the network. The dosing volume is the
amount of liquid pumped or siphoned during each cycle minus the amount which
drains back from the system after each dose.
2) Reserve capacity. If a single pump is used, a reserve
capacity equal to one day's average sewage flow shall be provided. A reserve
capacity is not required if multiple pumps or siphons are used.
3) A high water alarm switch shall be installed 2-3 inches above
the pump or siphon activation level. The switch shall be on a circuit separate
from the pump controls.
4) The pump or pumps shall be of a submersible type, designed for
corrosive liquids. The control switches shall be corrosion resistant. All
electrical contacts and relays shall be mounted outside the chamber. Provisions
shall be made to prevent gases in the chamber from following the electrical
conduits into the control box.