77 Ill. Adm. Code 976.180
Progress Reports
Section 976.180 Progress Reports
a) Each
grantee shall submit a progress report to the Department every 12 months from
the date that the grant agreement is executed until the project is complete.
The progress report is due within 10 calendar days after the anniversary date
of the grant agreement. The progress report shall include the following:
1) The
current status of the project, including the percentage of the project
finished, components finished and components yet to be finished;
2) The
cost incurred to date and an itemized listing of the total current estimated
project costs compared to the approved amounts;
3) The
anticipated date of completion; and
4) The
notarized signature of the grantee's Chief Executive Officer stating that this
is a true and complete report on the project's status.
b) Failure
to provide progress reports within the prescribed time frames will result in
the Department pursuing the recovery of grant funds (see Section 976.140).