77 Ill. Adm. Code 976.190
Project Completion
Section 976.190 Project Completion
Each grantee shall notify the Department within 30 calendar
days following the project's completion.
a) The
completion notice will provide a notarized statement that certifies the
following:
1) All
project costs and sources of funds;
2) That
all funds attributed to the grant award have been expended;
3) That
the costs reported are the final costs required to complete the project and
there are no additional or associated costs; and,
4) That
no portion of the grant was used
to pay for
any on-going operational
costs, outstanding debt or an endowment or other invested fund.
(Section
2310-640(a) of the Act)
b) The notarized statement
shall be signed by the grantee's Chief Executive Officer.
c) Grantees
whose projects are subject to CON requirements shall also document that the
Health Facilities and Services Review Board has deemed the project complete
(see 77 Ill. Adm. Code 1130.770). Documentation shall consist of a letter from
the Health Facilities and Services Review Board attesting that the project is
complete.
d) Grantees
whose projects are pending approval in accordance with the requirements of the
Hospital Licensing Act shall also provide a copy of the Permanent Occupancy or
Notice of System Acceptance letter (whichever is applicable) issued by the
Department.
e) Failure
to provide the completion notice within the prescribed time frame will result
in the Department pursuing the recovery of grant funds (see Section 976.140).