83 Ill. Adm. Code 460.420
Meter Tests Requested by Customer
Section 460
Section 460.420 Meter Tests
Requested by Customer
a) Upon customer request, the MSP shall test the customer's meter
within 30 days after receiving the request, unless the customer agrees to a
later time. The meter test shall be performed between 7 a.m. and 4 p.m. Monday
through Friday, excluding holidays, unless some other time is agreed upon by
the MSP and the customer. The test shall be performed at the meter installation
location and in the customer's presence, unless the customer gives consent for
the meter to be removed and/or tested outside the customer's presence.
b) If the customer's meter has been tested at the request of an
entity or customer while in service at the same location within the past six
months, the MSP may provide the results of that test in reply to the customer's
request in lieu of the test specified in subsection (a).
c) An MSP shall not require any payment from the customer for a
meter test, unless a test has been performed on that meter at that customer's
request within the previous twelve months, or information has been provided as
in subsection (b) within the past six months. In such cases, the customer shall
be required to pay $40 to the MSP. The MSP shall refund the $40 deposit to the
customer if the MSP finds that the meter over-registers by more than 2%.
d) Commission referee tests
1) Upon written application to the Commission by any customer,
the MSP providing metering service shall test the customer's meter within 30
days after receiving notice of the written request from a Commission
representative, unless the customer agrees to a later time. The application for
a Commission referee test shall be accompanied by a fee of $20. The MSP shall
conduct this test under the supervision of a representative of the Commission.
2) On receipt of the request from a customer, a Commission
representative shall notify the MSP. After the MSP has received notice that
application has been made for a referee test, the MSP shall not disturb the
meter in any way, unless the customer or the Commission representative gives
written permission for the meter to be removed.
3) The MSP shall furnish to the Commission's representative such
assistance as may be required to make the test. The Commission's representative
shall make a written report of the results of the test to the customer within
30 days after the test.
4) If upon test the meter is found to over-register by more than
2%, the MSP shall reimburse the customer the amount paid to the Commission for
the test. The MSP shall also make any necessary metering data adjustment.
e) No MSP shall be required to perform more than two tests of the
same meter installed at the same location at customer request within a twelve
month period, unless a Commission referee test is requested. After a Commission
referee test, the MSP shall not be required to test the same meter for a period
of at least twelve months.