83 Ill. Adm. Code 466.100
Level 2 Expedited Review
Section 466.100 Level 2 Expedited Review
An EDC shall use the Level 2 review procedure for
interconnection requests that meet the Level 2 criteria in Section 466.80(b). An
EDC may not impose additional requirements for Level 2 reviews that are not
specifically authorized under this Section unless the applicant agrees.
a) The
EDC shall evaluate the potential for adverse system impacts using the following
screens, which shall be satisfied:
1) Until
December 31, 2023, for interconnection of a proposed DER facility to a radial
distribution circuit, the aggregate export capacity of the DER facilities connected
to the distribution circuit, including the proposed DER facility, may not
exceed 100% of the minimum load (or 15% of the maximum load if minimum data are
unavailable) normally supplied by the distribution circuit or line section. After
December 31, 2023, for interconnection of a proposed DER facility to a radial
distribution circuit, the aggregate export capacity of the DER facilities
connected to the distribution circuit, including the proposed DER facility, may
not exceed 100% of the minimum load normally supplied by the distribution
circuit or line section.
2) For
interconnection of a proposed DER facility to the load side of spot network
protectors, the proposed DER facility shall utilize an inverter-based equipment
package. The customer interconnection equipment proposed for the DER facility
must be lab-certified and, when aggregated with other generation, the nameplate
capacity may not exceed 5% of a spot network's maximum load.
3) The
proposed DER facility, in aggregate with other generation on the distribution
circuit, may not contribute more than 10% to the distribution circuit's maximum
fault current at the point on the primary line nearest the point of
interconnection.
4) The
proposed DER facility, in aggregate with other generation on the distribution
circuit, shall not cause any distribution protective devices and equipment
including substation breakers, fuse cutouts, and line reclosers, or other
customer equipment on the electric distribution system to be exposed to fault
currents exceeding 90% of their short circuit interrupting capability. However,
if fault currents exceed 100% of the EDC's equipment short circuit interrupting
capability even without the DER being interconnected, the EDC shall replace the
equipment at its own expense, and interconnection may proceed under Level 2.
5) When
a customer-generator facility is to be connected to 3-phase, 3-wire primary EDC
distribution lines, a 3-phase or single-phase generator shall use a
phase-to-phase primary connection. This screen does not apply to DER
facilities with a nameplate capacity below 11 kVA.
6) When
a customer-generator facility is to be connected to 3-phase, 4-wire primary EDC
distribution lines, a 3-phase or single-phase generator shall use a grounded
line-to-neutral primary connection. This screen does not apply to DER
facilities with a nameplate capacity below 11 kVA.
7) When
the proposed DER facility is to be interconnected on single-phase shared
secondary line, the aggregate export capacity on the shared secondary line,
including the proposed DER facility, may not exceed 20 kVA. In the instance
where the proposed DER facility is below 100 kVA and uses acceptable means for
controlling export as set forth in Section 466.75, the export capacity of the
proposed DER facility will be used.
8) When
a proposed DER facility is single-phase and is to be interconnected on a center
tap neutral of a 240 volt service, its addition may not create an imbalance
between the two sides of the 240 volt service of more than 20% of the nameplate
kVA rating of the service transformer.
9) The
nameplate capacity of a DER facility, in aggregate with other DER facilities'
nameplate capacity interconnected to the distribution side of a substation
transformer feeding the circuit where the DER facility proposes to
interconnect, may not exceed 10 MVA in an area where there are known or posted
transient stability limitations to generating units located in the general
electrical vicinity.
b) The Level 2
interconnection shall use the following procedures:
1) The
applicant submits an interconnection request using the appropriate form and the
Level 2 application fee (see Appendix C).
2) Within
10 business days after receiving the interconnection request, the EDC shall
inform the applicant as to whether the interconnection request is complete. If
the request is incomplete, the EDC shall specify what materials are missing and
the applicant has 10 business days to provide the missing information or the
interconnection request shall be deemed withdrawn.
3) After
an interconnection request is deemed complete, the EDC shall assign a queue
position based upon the date that the interconnection request is determined to
be complete. The EDC shall then inform the applicant of its queue position.
4) If,
after determining that the interconnection request is complete, the EDC determines
that it needs additional information to evaluate the DER facility's adverse
system impact, it shall request this information. The EDC may not restart the
review process or alter the applicant's queue position because it requires the
additional information. The EDC can extend the time to finish its evaluation
only to the extent of the delay required for receipt of the additional
information. In order to withdraw an interconnection request, the EDC must
first send a notification to the applicant of its intent to withdraw, and the
applicant must not have sent the information requested by the EDC within 5
business days after receipt of the notice.
5) Within
20 business days after the EDC notifies the applicant it has received a
completed interconnection request, the EDC shall:
A) Evaluate
the interconnection request using the Level 2 screening criteria.
B) Provide
the applicant with the EDC's evaluation, including a written technical
explanation. If one or more screens are not passed, the EDC shall provide, in
writing, the specific screens that the application failed, including the
technical reason for failure. The EDC shall provide information and detail
about the specific system threshold or limitation causing the application to
fail the screen. If an EDC does not have a record of receipt of the
interconnection request and the applicant can demonstrate that the original
interconnection request was delivered, the EDC shall expedite its review to
complete the evaluation of the interconnection request within 20 business days
after the applicant's demonstration.
c) When
an EDC determines that the interconnection request passes the Level 2 screening
criteria contained in subsection (a), the interconnection request passes the
Supplemental Review contained in subsection (f), or the EDC determines that the
DER facility can be interconnected safely and will not cause adverse system
impacts, even if it fails one or more of the Level 2 screening criteria, it
shall provide the applicant with a standard DER interconnection agreement (see
Appendix D) within the following timeframes:
1) If the proposed
interconnection requires no construction of facilities by the EDC on its own
system, the interconnection agreement shall be provided within 5 business days
after the notification of Level 2 review results.
2) If the proposed
interconnection requires only minor system modifications, the EDC shall notify
the applicant of the required minor system modifications when it provides the
Level 2 results. The applicant must inform the EDC if the applicant elects to
continue the application and pay the fee specified in the EDC's tariff. If the
applicant makes such an election, the EDC shall provide to the applicant the
interconnection agreement, along with a non-binding good faith cost estimate
and construction schedule for the required upgrades within 30 business days
after the EDC receives such an election and the payment of the fee.
3) If
the proposed interconnection requires more than minor system modifications, the
EDC shall notify the applicant of that requirement when it provides the Level 2
or supplemental review results. The applicant must inform the EDC if the
applicant elects to continue the application. If the applicant makes such an
election, the EDC may elect to:
A) provide
a standard DER interconnection agreement (see Appendix D), along with a
non-binding good faith cost estimate and construction schedule for the required
upgrades within 45 business days after the EDC receives such an election and
the applicant pays the fee specified in the EDC's tariff; or
B) notify
the applicant that an interconnection facilities study under Section
466.120(e)(3) must be performed to determine the necessary upgrades. If the
applicant elects to proceed with an interconnection facilities study, the EDC
shall proceed with the interconnection facilities study according to the
timeframes and process in Section 466.120(e)(3).
d) Within
30 business days after receipt of the standard DER interconnection agreement,
the applicant shall sign and return the agreement to the EDC. If the applicant
does not sign and return the agreement within 30 business days, the
interconnection request shall be deemed withdrawn unless the applicant requests
a 15-business-day extension in writing. The initial request for extension may
not be denied by the EDC. When the EDC constructs an additional review under
the provisions of subsection (f), the interconnection of the DER facility shall
proceed according to milestones agreed to by the parties in the standard DER
interconnection agreement.
e) The DER
facility is not permitted to operate until:
1) All
requirements in the standard DER interconnection agreement are satisfied;
2) The DER
facility is approved by the electric code officials with jurisdiction over the
interconnection;
3) The
applicant provides a certificate of completion (see Appendix B) to the EDC.
Completion of local inspections may be designated on inspection forms used by
local inspecting authorities; and
4) The
witness test is successfully completed if required by the EDC or if the witness
test is waived according to Article 2.1.1 of Appendix D.
f) When
a DER facility fails to meet one or more of the Level 2 screens contained in subsection
(a), the EDC shall provide the applicant the opportunity to amend its
application one time to address the screen failure and offer to perform a supplemental
review in accordance with the following subsections and provide the applicant
with a non-binding estimate for the costs of the supplemental review. If the
applicant chooses to amend the application to address the specific screens that
failed, the applicant must submit updated application materials demonstrating
the redesign within 10 business days after receiving the screen results from
the EDC. If the applicant chooses to have a supplemental review performed, the EDC
shall undertake the supplemental review only after the applicant pays for the supplemental
review.
1) If
the applicant accepts the offer of a supplemental review, the applicant shall
agree in writing and pay the amount of the EDC's good faith estimate of the
costs of that review, both within 15 business days after the offer. If the
written agreement and payment have not been received by the EDC within that
timeframe, the interconnection request shall be considered withdrawn by the applicant.
2) The applicant
may specify the order in which the EDC will complete the screens in this Section.
3) The applicant
shall be responsible for the EDC's actual costs for conducting the supplemental
review. The applicant must pay any additional costs that exceed the good faith
estimate within 20 business days after receipt of the invoice or resolution of
any dispute. If the initial payment exceeds the invoiced actual costs, the EDC
will return that excess within 20 business days after the invoice without
interest.
4) Within
30 business days following receipt of the payment for a supplemental review,
the EDC shall perform a supplemental review using the screens set forth in this
subsection (f)(4); notify in writing the applicant of the results; and include
with the notification copies of the analysis and data underlying the EDC's
determinations under the screens.
A) Minimum Load Screen
When 12
months of line section minimum load data (including onsite load but not station
service load served by the proposed DER facility) are available, the aggregate
export capacity of the
generating
facility on the line section is less than 100% of the minimum load for all line
sections bounded by automatic sectionalizing devices upstream of the proposed DER
facility. If minimum load data is not available, the EDC shall include the
reasons that it is unable to determine minimum load in its supplemental review
results notification under this Section.
This
screen does not apply to non-exporting systems or those that are proposing to
add no new export capacity.
i) The type of generation used by the proposed DER
facility will be taken into account when determining circuit or line section
minimum load relevant to the application of this screen. Solar PV generation
systems with no energy storage use daytime minimum load (i.e., 10 a.m. to 4
p.m. for fixed panel systems and 8 a.m. to 6 p.m. for PV systems utilizing
tracking systems), while all other generation uses absolute minimum load.
The EDC shall apply this screen using the operating profile
and system design designated in the interconnection request and accompanying
attachments. For example, the EDC shall evaluate the maximum export capacity
during the hours of the day designated by the customer as operational and shall
take into account any export controls.
ii) Only the net injection into the EDC's electric
system will be considered as part of the aggregate
export capacity
.
In the instance where the proposed DER facility uses
acceptable means for controlling export as set forth in Section 466.75, only
the net power injection into the EDC's electric system will be considered as
part of the aggregate export capacity.
iii) For evaluating this screen, the EDC will not
include as part of the aggregate
export
capacity
any existing DER facility export
capacity already reflected in the minimum load data.
B) Voltage and Power Quality Screen
The
project, considered in aggregate with existing generation, must meet the
following requirements: the voltage regulation can be maintained in compliance
with relevant requirements under all system conditions; the voltage fluctuation
is within the EDC's acceptable limits; and the harmonic levels meet limits
recommended by IEEE Standard 519-2014:
Recommended Practice and
Requirements for Harmonic Control in Electric Power
Systems.
C) Safety and Reliability Screen
The
location of the proposed DER facility and the aggregate generation capacity on
the line section do not create impacts to safety or reliability that cannot be
adequately addressed without application of the Level 4 process. The EDC shall
give due consideration to the following and other factors in determining
potential impacts to safety and reliability in applying this screen:
i) whether the line section has significant
minimum loading levels dominated by a small number of customers (e.g., several
large commercial customers);
ii) whether the loading along the line section is
uniform or even;
iii) whether the proposed DER facility is located
in close proximity to the substation (i.e., less than 2.5 electrical circuit
miles), and whether the line section from the substation to the point of interconnection
is a main line rated for normal and emergency ampacity;
iv) whether the proposed DER facility incorporates
a time delay function to prevent reconnection of the generator to the system
until system voltage and frequency are within normal limits for a prescribed
time;
v) whether operational flexibility is reduced by
the proposed DER facility, such that transfer of the line section of the DER
facility to a neighboring distribution circuit/substation may trigger overloads
or voltage issues; and
vi) whether the proposed DER facility employs
equipment or systems certified by a nationally recognized testing laboratory
(NRTL) to address technical issues such as, but not limited to, islanding,
reverse power flow or voltage quality.
5) If
the proposed interconnection passes the supplemental review screening in this Section,
the EDC shall provide the applicant with an executable interconnection
agreement pursuant to subsections (c), (d) and (e).
g) If
the DER facility is not approved under a Level 2 review, the EDC shall provide
the applicant with written notification explaining its reasons for denying the
interconnection request. The EDC shall specify which screens the application
failed, including the technical reason for failure, and the data and the
analysis supporting the supplemental review. The EDC shall provide information
and detail about the specific system threshold or limitation, preventing
determination of required system modification without further study. If the
applicant chooses to revise the application to address the specific screens
that failed, the customer must submit updated application materials
demonstrating the redesign within 10 business days after receiving the review results
from the EDC and pay an additional review cost. However, this redesign shall
not include an increase in export capacity and shall not include a change in
the proposed location of the DER facility. Increases in export capacity or
changes in facility location shall require a new interconnection request and
associated fees. The EDC will evaluate whether the redesign addresses the
screen failure and provide the applicant the results of this evaluation in 10
business days. This option shall only be available one time during the
screening phase of the Level 2 process.
h) If
the applicant chooses not to redesign the project or the redesign does not
result in passage of the screens, the applicant may submit a new
interconnection request for consideration under a Level 4 interconnection
review. The queue position assigned to the Level 2 interconnection request shall
be retained, provided that the new interconnection request is made by the
applicant within 15 business days after notification that the current
interconnection request is denied.