83 Ill. Adm. Code 466.110
Level 3 Expedited Review
Section 466.110 Level 3 Expedited Review
An EDC shall use the Level 3 expedited review procedure for
an interconnection request that meets the criteria in Section 466.80(c). An EDC
may not impose additional requirements for Level 3 reviews not specifically
authorized under this section unless the applicant agrees.
a) A Level 3
interconnection shall use the following procedures:
1) The
applicant submits an interconnection request using the appropriate form and the
Level 3 application fee (see Appendix C).
2) Within
10 business days after receiving the interconnection request, the EDC shall
inform the applicant as to whether the interconnection request is complete. If
the request is incomplete, the EDC shall specify what materials are missing and
the applicant has 10 business days to provide the missing information, or the
interconnection request shall be deemed withdrawn.
3) After
an interconnection request is deemed complete, the EDC shall assign a queue
position to it based upon the date the interconnection request is determined to
be complete. The EDC shall then inform the applicant of its queue position.
4) If,
after determining that the interconnection request is complete, the EDC
determines that it needs additional information to evaluate the DER facility's
adverse system impact, it shall request this information. The EDC may not
restart the review process or alter the applicant's queue position because it
requires the additional information. The EDC can extend the time to finish its
evaluation only to the extent of the delay is required for receipt of the
additional information. If the applicant does not provide this additional
information within 15 business days, the EDC may deem the interconnection
request withdrawn.
5) Interconnection
requests meeting the requirements set forth in Section 466.80(c)(1) for
non-exporting DER facilities interconnecting to an area network shall be
presumed to be appropriate for interconnection. The EDC shall process the
interconnection request to area networks using the following procedures:
A) The EDC
shall evaluate the interconnection request under Level 2 interconnection review
procedures as set forth in Section 466.100(a) except that the EDC has 25
business days to evaluate the interconnection request against the screens to
determine whether interconnecting the DER facility to the EDC's area network
has any potential adverse system impacts. In applying the Level 2 screens set
forth in Section 466.100(a) for projects on area networks, the EDC may evaluate
the proposed DER facility using nameplate capacity and not the export capacity
for screens 1 and 7 if it determines that is appropriate.
B) If the
Level 2 screens for area networks identify potential adverse system impacts,
the EDC may determine, at its sole discretion, that it is inappropriate for the
DER facility to interconnect to the area network under Level 3 review, and the
interconnection request is denied. The applicant may submit a new
interconnection request for consideration under Level 4 procedures at the queue
position assigned to the Level 3 interconnection request, if the new
interconnection request is made within 15 business days after notification that
the current application is denied.
6) For
interconnection requests that meet the requirements of Section 466.80(c)(2) for
non-exporting DER facilities interconnecting to a radial distribution circuit,
the EDC shall evaluate the interconnection request under the Level 2 expedited
review in Section 466.100(a).
b) For a
DER facility that satisfies the criteria in Section 466.110(a)(5) or (a)(6),
the EDC shall approve the interconnection request and provide a standard
interconnection agreement (see Appendix D) for the applicant to sign within the
following timeframes:
1) If the proposed
interconnection requires no construction of facilities by the EDC on its own
system, the interconnection agreement shall be provided within 5 business days
after the notification of Level 3 review results.
2) If the proposed
interconnection requires only minor system modifications, the EDC shall notify
the applicant of that requirement when it provides the Level 3 results. The
applicant must inform the EDC if the applicant elects to continue the
application and pay the fee specified in the EDC's tariff. If the applicant
makes such an election, the EDC shall provide the interconnection agreement,
along with a non-binding good faith cost estimate and construction schedule for
those upgrades, to the applicant within 30 business days after the EDC receives
such an election and the payment of the fee.
3) If
the proposed interconnection requires more than minor system modifications, the
EDC shall notify the applicant of that requirement when it provides the Level 3
results. The applicant must inform the EDC if the applicant elects to proceed
with the interconnection. If the applicant makes such an election, the EDC may
elect to:
A) provide
a standard DER interconnection agreement (see Appendix D), along with a
non-binding good faith cost estimate and construction schedule for those
upgrades within 45 business days after the EDC receives such an election and
the applicant pays the fee specified in the EDC's tariff; or
B) notify
the applicant that an interconnection facilities study must be performed pursuant
to Section 466.120(e)(3). If the applicant elects to proceed with an
interconnection facilities study, the EDC shall proceed with the
interconnection facilities study according to the timeframes and process in
Section 466.120(e)(3).
c) Within
30 business days after receipt of the standard DER interconnection agreement,
the applicant shall complete, sign and return the agreement to the EDC. If the
applicant does not sign the standard DER interconnection agreement within 30
business days, the request shall be deemed withdrawn, unless the applicant
requests a 15 business day extension in writing. An initial request for
extension may not be denied by the EDC. After the standard DER interconnection
agreement is signed by the parties, interconnection of the DER facility shall
proceed according to any milestones agreed to by the parties in the standard DER
interconnection agreement.
d) The DER
facility is not permitted to operate until:
1) All
requirements in the interconnection agreement are satisfied;
2) The DER
facility is approved by the electric code officials with jurisdiction over the DER
facility;
3) The
applicant provides a certificate of completion (see Appendix B) to the EDC; and
4) The
witness test is successfully completed, if required by the EDC or if the
witness test is waived according to Article 2.1.1 of Appendix D.
e) If
the DER facility is not approved under a Level 3 review, the EDC shall provide
the applicant with written notification explaining its reasons for denying the
interconnection request. The applicant may submit a new interconnection
request for consideration under a Level 4 interconnection review. The queue
position assigned to the Level 3 interconnection request shall be retained,
provided that the new interconnection request is made within 15 business days
after notification that the current interconnection request is denied.