83 Ill. Adm. Code 466.80
Determining the Review Level
Section 466.80 Determining the Review Level
An EDC shall determine whether an interconnection request
should be processed under the Level 1, 2, 3 or 4 procedures by using the
following screens:
a) An
EDC shall use Level 1 procedures to evaluate all interconnection requests to
connect a DER facility when:
1) The
applicant has filed a Level 1 application; and
2) The DER
facility has an export capacity of 25 kW or less and a nameplate capacity of 50
kW or less. If the DER facility's export capacity is not limited, the
nameplate capacity cannot exceed 25 kW; and
3) The DER
facility is inverter-based; and
4) The
customer interconnection equipment proposed for the DER facility is lab-certified.
b) An
EDC shall use Level 2 procedures for evaluating interconnection requests when:
1) The
applicant has filed a Level 2 application;
2) For
certified inverter-based systems, the permissible nameplate capacity is limited
according to the voltage of the line at the proposed point of interconnection
as follows:
Line Voltage
Level 2 Eligibility
< 5 kV
≤ 500 kW
≥ 5 kV and
< 15 kV
≤ 3 MW
≥ 15 kV and
< 30 kV
≤ 4 MW
≥ 30 kV and
≤ 69 kV
≤ 5 MW
3) All DER
facilities connecting to lines greater than 69 kV are ineligible for Level 2
review regardless of size. All synchronous and induction machines must have a
nameplate capacity no larger than 2 MW to be eligible;
4) The
interconnection equipment proposed for the DER facility is lab-certified; and
5) The
proposed interconnection is to a radial distribution circuit or a spot network
limited to serving one customer.
c) An
EDC shall use Level 3 review procedures for evaluating interconnection requests
to area networks and radial distribution circuits where power will not be
exported based on the following criteria.
1) For
interconnection requests to the load side of an area network, the following
criteria shall be satisfied to qualify for a Level 3 expedited review:
A) The
applicant has filed a Level 3 application; and
B) The
nameplate capacity of the DER facility is less than or equal to 50 kW; and
C) The
proposed DER facility uses a lab-certified inverter-based equipment package;
and
D) The DER
facility uses acceptable means for non-export controls as set forth in Section
466.75; and
E) The
aggregate of all generation on the area network does not exceed the lower of 5%
of an area network's maximum load or 50 kVA.
2) For
interconnection requests to a radial distribution circuit, the following
criteria shall be satisfied to qualify for a Level 3 expedited review:
A) The
applicant has filed a Level 3 application; and
B) The aggregate
export capacity of all the generators on the circuit, including the proposed DER
facility, is 10 MVA or less; and
C) The DER
facility will use acceptable means for controlling export as set forth in Section
466.75; and
D) The DER
facility is not served by a shared transformer.
d) An
EDC shall use the Level 4 study review procedures for evaluating
interconnection requests when:
1) The
interconnection request does not qualify for Level 1, 2, or 3 expedited review;
2) The interconnection
request failed one or more screens of a Level 1, 2, or 3 expedited review, or a
Level 2 supplemental review; or
3) The
applicant has filed a Level 4 application.