83 Ill. Adm. Code 466.APPENDIX A
A Level 1 Application and Contract
Section 466.APPENDIX A Level 1
Application and Contract
Illinois
Standard Distributed Energy Resources Interconnection
Level 1
Interconnection
Request Application Form and
Conditional
Agreement to Interconnect
(Lab-Certified
Inverter-Based Distributed Energy Resources Facilities 25 kW and Smaller)
An application fee of
$50.00 must be submitted with the application.
Interconnection Applicant
Contact Information
Name:
Mailing Address:
City:
State:
Zip Code:
Telephone (Daytime):
(Evening):
Facsimile Number:
E-Mail Address:
Alternate Contact Information (if different from Applicant)
Name:
Mailing Address:
City:
State:
Zip Code:
Telephone (Daytime):
(Evening):
Facsimile Number:
E-Mail Address:
Equipment Contractor
Name:
Mailing Address:
City:
State:
Zip Code:
Telephone (Daytime):
(Evening):
Facsimile Number:
E-Mail Address:
Electrical Contractor (if Different from Equipment
Contractor):
Name:
Mailing Address:
City:
State:
Zip Code:
Telephone (Daytime):
(Evening):
Facsimile Number:
E-Mail Address:
License number:
Active License?
Yes
No
Is the Interconnection Customer requesting Net Metering in
accordance with 83 Ill. Adm. Code 465?
Yes No
Distributed Energy Resources
Facility ("Facility") Information
Facility Address:
City:
State:
Zip Code:
Electric Distribution Company
(EDC) serving Facility site:
Electric Supplier (if
different from EDC):
If existing EDC electric service exists at point of
interconnection:
Account Number of site:
EDC billing meter ID
Inverter Manufacturer:
Model:
Is the inverter lab-certified as that term is defined in
the Illinois Distributed Energy Resources Interconnection Standard? Yes No
(If yes, attach manufacturer's technical specifications
and label information from a nationally recognized testing laboratory.)
Generation Facility Nameplate
Rating:
(kW)
(kVA)
(AC Volts)
Total Facility Nameplate
Capacity:
(kW)
(kVA)
Prime Mover:
Photovoltaic
Reciprocating Engine
Fuel Cell
Turbine
Other
Energy Source:
Solar
Wind
Hydro
Diesel
Storage
Combination
Natural Gas
Fuel Oil
Other
Commissioning Date:
(If the Commissioning Date changes,
the interconnection customer must inform the EDC as soon as it is aware of the
changed date.)
Limited Export and Non-Export Controls Information
Manufacturer:
Model Number:
M
Limited Export or Non-Export?
Limited Export
Non-Export
Control Type:
Reverse Power Protection
Minimum Power Protection
Relative
Distributed Energy Resource Rating
Configured Power Rating
Limited
Export Power Control Systems
Limited
Export using mutually agreed-upon means
Directional
Power Protection
Export Capacity Value (in kW):
Control Power Setting:
Control Power Time Delay (if any):
Battery Storage Facility Information (If Applicable)
Do the batteries share an
inverter with a renewable energy system?
☐
Yes
☐
No
Does the applicant intend to have the batteries
c
h
a
rg
e
d
by
t
h
e
d
ist
r
i
b
u
ti
o
n
gr
i
d
?
☐
Yes
☐
No
System Manufacturer:
Model:
Battery Type:
Battery Charge/Discharge
Rating (kW AC):
Maximum Battery
Charge/Discharge Rate (kW AC per second):
Battery Energy Capacity (kWh):
Power Factor Settings Range:
Battery Storage Inverter Information
Energy System
Manufacturer:
Model:
Type:
☐
Forced
☐
Commutated
Line Commutated Rated Output
Watts:
Volts:
Efficiency:
____ %
Power Factor:
____ %
Inverter IEEE 1547 / UL 1741 Listed:
☐
Yes
☐
No
Number of Inverters:
Total Capacity:
kW
DC Source / Prime Mover:
- Rating:
kW Rating:
kVA Rated Voltage:
Volts
Open Circuit Voltage (If Applicable):
Volts
Rated Current:
Amps
Battery Operational Information
Backup – allows for partial or whole home transition to
off-grid during a grid outage.
☐
Yes
☐
No
Solar Self-Powered – the battery will charge from the
renewable energy source during normal operation and discharge to serve loads
behind your meter.
☐
Yes
☐
No
Solar Non-Export – limits the export of energy to the grid
to zero for both the battery and inverter, even if the battery system is fully
charged and there is excess renewable source energy.
☐
Yes
☐
No
Time-Based Control (sometimes called time-of-use or TOU
mode) – the battery charges during off-peak hours and discharges to serve
onsite loads during on-peak hours.
☐
Yes
☐
No
Describe any other intended
operation of the battery:
Insurance Disclosure
The attached terms and conditions contain provisions related
to liability and indemnification, and should be carefully considered by the
interconnection customer. The interconnection customer shall carry general
liability insurance coverage, such as, but not limited to, homeowner's
insurance. Whenever possible, the interconnection customer shall name the EDC
as an additional insured on its homeowner's insurance policy, or similar policy
covering general liability.
Customer Signature
I hereby certify that: (1) I have read and understand the
terms and conditions which are attached hereto by reference; (2) I hereby
agree to comply with the attached terms and conditions; and (3) to the best of
my knowledge, all of the information provided in this application request form
is complete and true.
Applicant Signature:
Title:
Date:
………………………………………………………………………………………………………
Conditional Agreement to Interconnect Distributed Energy
Resources
Facility
Receipt of the application fee is acknowledged and, by its
signature below, the EDC has determined the interconnection request is complete.
Interconnection of the distributed energy resources facility is conditionally
approved contingent upon the attached terms and conditions of this Agreement,
the return of the attached Certificate of Completion, duly executed
verification of electrical inspection and successful witness test.
EDC Signature:
Date:
Name:
Title:
Terms and
Conditions for Interconnection
1)
Construction
of the Distributed Energy Resources Facility
. The interconnection customer
may proceed to construct (including operational testing not to exceed 2 hours)
the distributed energy resources (DER) facility, once the conditional Agreement
to interconnect a DER facility has been signed by the EDC.
2)
Final
Interconnection and Operation.
The interconnection customer may operate
the DER facility and interconnect with the EDC's electric distribution system after
all of the following have occurred:
a) Electrical
Inspection: Upon completing construction, the interconnection customer shall
cause the DER facility to be inspected by the local electrical inspection
authority, who shall establish that the DER facility meets local code
requirements.
b) Certificate
of Completion: The interconnection customer shall provide the EDC with a copy
of the Certificate of Completion with all relevant and necessary information fully
completed by the interconnection customer, as well as an inspection form from
the local electrical inspection authority demonstrating that the DER facility
passed inspection.
c) The EDC has completed
its witness test as per the following:
i) Within
10 business days of the commissioning date, the EDC must, upon reasonable
notice and at a mutually convenient time, conduct a witness test of the DER
facility to ensure that all equipment has been appropriately installed and that
all electrical connections have been made in accordance with the applicable
codes.
ii) If
the EDC does not perform the witness test within the 10 business days after the
commissioning date or such other time as is mutually agreed to by the Parties,
the witness test is deemed waived unless the EDC cannot do so for good cause. In
these cases, upon EDC request, the interconnection customer shall agree to
another date for the test within 10 business days after the original scheduled
date.
3)
IEEE
1547.
The DER facility shall be installed, operated and tested in
accordance with the requirements of The Institute of Electrical and Electronics
Engineers, Inc. (IEEE), 3 Park Avenue New York, NY 10016-5997, Standard 1547
(2003) "Standard for Interconnecting Distributed Resources with Electric
Power Systems."
4)
Access.
The EDC shall have direct, unabated access to the disconnect switch and
metering equipment of the DER facility at all times. The EDC shall provide 5
business days' notice to the customer prior to using its right of access except
in emergencies.
5)
Metering.
Any required metering shall be installed pursuant to Illinois Commerce
Commission approved tariffs.
6)
Disconnection.
The EDC may disconnect the DER facility upon any of the following conditions,
but must reconnect the DER facility once the condition is cured:
a) For
scheduled outages, provided that the DER facility is treated in the same manner
as EDC's load customers;
b) For unscheduled outages
or emergency conditions;
c) If
the DER facility does not operate in the manner consistent with this Agreement;
d) Improper installation or
failure to pass the witness test;
e) If
the DER facility is creating a safety, reliability or a power quality problem;
or
f) The
interconnection equipment used by the DER facility is de-listed by the Nationally
Recognized Testing Laboratory that provided the listing at the time the
interconnection was approved.
7)
Indemnification
.
The interconnection customer shall indemnify and defend the EDC and the EDC's
directors, officers, employees, and agents from all damages and expenses
resulting from any third party claim arising out of or based upon the
interconnection customer's (a) negligence or willful misconduct or (b) breach
of this Agreement. The EDC shall indemnify and defend the interconnection
customer and the interconnection customer's directors, officers, employees, and
agents from all damages and expenses resulting from a third party claim arising
out of or based upon the EDC's (a) negligence or willful misconduct or (b)
breach of this Agreement.
8)
Insurance
.
The interconnection customer shall provide the EDC with proof that it has a
current homeowner's insurance policy, or other general liability policy, and, when
possible, the interconnection customer shall name the EDC as an additional
insured on its homeowner's insurance policy, or similar policy covering general
liability.
9)
Limitation
of Liability
.
Each Party's liability to the other Party for any
loss, cost, claim, injury, liability, or expense, including reasonable attorney's
fees, relating to or arising from any act or omission in its performance of
this Agreement, shall be limited to the amount of direct damage actually
incurred. In no event shall either Party be liable to the other Party for any
indirect, incidental, special, consequential, or punitive damages of any kind
whatsoever.
10)
Termination
.
This Agreement may be terminated under the following conditions:
a) By
interconnection customer − The interconnection customer may terminate
this Agreement by providing written notice to the EDC. If the interconnection
customer ceases operation of the DER facility, the interconnection customer
must notify the EDC
b) By
the EDC − The EDC may terminate this Agreement if the interconnection
customer fails to remedy a violation of terms of this Agreement within 30
calendar days after notice, or such other date as may be mutually agreed to
prior to the expiration of the 30 calendar day remedy period. The termination
date may be no less than 30 calendar days after the interconnection customer
receives notice of its violation from the EDC.
11)
Modification
of Distributed Energy Resources Facility
. The interconnection customer
must receive written authorization from the EDC before making any changes to
the DER facility that could affect the EDC's distribution system. If the
interconnection customer makes such modifications without the EDC's prior written
authorization, the EDC shall have the right to disconnect the DER facility.
12)
Permanent
Disconnection.
In the event the
Agreement is
terminated, the
EDC shall have the right to disconnect its facilities or direct the
interconnection customer to disconnect its DER facility.
13)
Disputes.
Each Party agrees to attempt to resolve all disputes regarding the
provisions of this Agreement that cannot be resolved between the two Parties
pursuant to the dispute resolution provisions found in 83 Ill. Adm. Code
466.130.
14)
Governing
Law, Regulatory Authority, and Rules.
The validity, interpretation and
enforcement of this Agreement and each of its provisions shall be governed by
the laws of the State of Illinois. Nothing in this Agreement is intended to
affect any other agreement between the EDC and the interconnection customer.
15)
Survival
Rights
. This Agreement shall remain in effect after termination to the
extent necessary to allow or require either Party to fulfill rights or
obligations that arose under the Agreement.
16)
Assignment/Transfer
of Ownership of the Distributed Energy Resources Facility
. This Agreement
shall terminate upon the transfer of ownership of the DER facility to a new
owner unless the transferring owner assigns the Agreement to the new owner, the
new owner agrees in writing to the terms of this Agreement, and the
transferring owner so notifies the EDC in writing prior to the transfer of
ownership.
17)
Definitions
.
Any term used herein and not defined shall have the same meaning as the defined
terms used in 83 Ill. Adm. Code 466 (the Illinois Distributed Energy Resources Interconnection
Standard).
18)
Notice
.
The Parties may mutually agree to provide notices, demands, comments, or
requests by electronic means such as e-mail. Absent agreement to electronic
communication, or unless otherwise provided in this Agreement, any written
notice, demand, or request required or authorized in connection with this
Agreement shall be deemed properly given if delivered in person, delivered by
recognized national courier service, or sent by first class mail, postage
prepaid, to the person specified below:
If to Interconnection Customer
:
Use the contact information
provided in the interconnection customer's application. The interconnection
customer is responsible for notifying the EDC of any change in the contact
party information, including change of ownership.
If to EDC
:
Use the contact information provided
below. The EDC is responsible for notifying the interconnection customer of
any change in the contact party information.
Name:
Mailing Address:
City:
State:
Zip Code:
Telephone (Daytime):
(Evening):
Facsimile Number:
E-Mail Address: