83 Ill. Adm. Code 467.45
Pre-Application Report
Section
467.45 Pre-Application Report
a) In addition
to the information described in Section 467.60, which may be provided in
response to an informal request, a potential applicant may submit a formal
written request form along with a non-refundable fee of $300 for a
pre-application report on a proposed project at a specific site. The EDC shall
provide the pre-application data described in this Section to the potential applicant
within 20 business days after receipt of the completed request form and payment
of the $300 fee. The pre-application report produced by the EDC is non-binding
and does not confer any rights; the potential applicant must successfully file
an application before it can interconnect with the EDC's system. The written
pre-application report request form shall include the following information to
clearly and sufficiently identify the location of the proposed point of interconnection:
1) project
contact information, including name, address, phone number and email address;
2) project
location (street address with nearby cross streets, town, and GPS coordinates
in decimal format);
3) meter
number, pole number or other equivalent information identifying proposed point
of interconnection, if available;
4) generator
type (e.g., solar, wind, combined heat and power, energy storage or inverter
system or fuel cells);
5) size (alternating current kW);
6) single or three-phase
generator configuration;
7) whether a
stand-alone generator is proposed (no onsite load, not including station
service);
8) whether new electric
service is required for the site. Include the existing minimum and maximum
on-site electrical demand (in kVA) and describe any expected changes to the
minimum and maximum on-site electrical demand (in kVA), including the timing of
those changes; and
9) the number
and capacity of each generator unit to be interconnected at the site specified
in the pre-application report request.
b) Using the
information provided in the pre-application report request form described in subsection
(a), the EDC shall identify the substation/area bus, bank or circuit likely to
serve the proposed point of interconnection. This selection by the EDC does not
necessarily indicate, after application of the relevant review process, that
this would be the circuit to which the project ultimately connects. The
potential applicant must request additional pre-application reports if
information about multiple points of interconnection is requested. Subject to subsection
(c), the pre-application report shall include the following information:
1) Identification
of up to two distribution circuits within one quarter mile of the proposed
point of interconnection, including the following information:
A) Substation
and circuit identifying information;
B) Feeder
configuration (e.g., radial or network);
C) Number and
size of phase conductors at the point of interconnection;
D) Distance to
three-phase (if applicable);
E) Primary
circuit voltage at the point of interconnection;
F) Existing
aggregate generation capacity interconnected to the identified substations and
circuits;
G) Aggregate
generation capacity and non-binding estimated costs associated with projects
earlier in the queue and planned for the identified substations and circuits;
H) Capacity of
the substation transformer, substation circuit equipment, and lowest rated
circuit equipment between the proposed point of interconnection and the
substation/area bus identified;
I) Circuit peak
and minimum load: estimated if actual is unavailable (i.e., minimum load from
10 a.m. to 4 p.m. Central Prevailing Time for fixed panel photovoltaic (PV)
systems, from 8 a.m. to 6 p.m. for PV systems using tracking systems, or
absolute minimum for non-PV and energy storage systems);
J) Approximate
circuit distance between the proposed point of interconnection and the
identified substation or area bus;
K) Size and type
of relevant protective devices between the proposed point of interconnection
and the substation/area bus identified, including:
i) Lowest
rated upstream recloser, where applicable; and
ii) Lowest
rated upstream fuse, where applicable;
L) Number of regulating
devices between the proposed point of interconnection and the substation/area
bus identified; and
M) For the EDC's
proposed point of interconnection, all existing or anticipated constraints that
might affect the interconnection.
2) Disclosure from
the EDC as to whether the aggregate contingent upgrades of the systems earlier
in the queue are estimated to exceed the following thresholds, if such
estimates are available:
A) Distribution
facility replacement/upgrades of $50,000;
B) Substation
transformer replacement/upgrades of $100,000; or
C) Transmission
replacement/upgrades of $100,000.
c) The
pre-application report need only include existing data. A pre-application
report request does not obligate the EDC to conduct a study or other analysis
of the proposed generator in the event that data is not readily available. If
the EDC cannot complete all or some of a pre-application report due to lack of
available data, the EDC shall provide the interconnection customer with a
pre-application report that includes the data that is available. The provision
of information on "available capacity" within the pre-application
report represents the best information available to the EDC at the time of the
reporting and does not imply that an interconnection up to this level may be
completed without impacts.