83 Ill. Adm. Code 467.50
Interconnection Request Review
Section 467.50 Interconnection Request Review
a) Applicants
seeking to interconnect a DER facility, or to revise a DER facility that has
already been interconnected, shall submit an interconnection request to the EDC
that owns the electric distribution system to which interconnection is sought.
Applicants shall use interconnection request forms approved by the Commission.
The EDC may require additional information from the Applicant if the EDC can
demonstrate that the additional information is necessary in order for the EDC
to conduct its review under this Part.
b) The
application fee is specified in the interconnection application form (see
Appendix B).
c) Interconnection
requests may be submitted electronically.
d) If
the timelines provided in this Part cannot be met due to the unique
characteristics of the proposed facility, parties shall negotiate timelines
that differ from those established in this Part. Alternative timelines may be
needed to account for project complexities, personnel requirements or other
outside factors regarding a particular project. If a mutual agreement is not
reached, parties may use the dispute resolution procedures in Section 467.80.