83 Ill. Adm. Code 467.APPENDIX E
E Interconnection System Impact Study Agreement
Section 467.APPENDIX E Interconnection System Impact
Study Agreement
Interconnection System
Impact Study Agreement
This agreement ("Agreement")
is made and entered into this
day of
by and between
("interconnection customer"), as an
individual person, or as a
organized and existing under the
laws of the State of
, and
("Electric Distribution
Company" (EDC)), a
existing under the laws of the
State of Illinois. Interconnection customer and EDC each
may be referred to as a "Party", or collectively as the
"Parties".
Recitals:
Whereas
, the interconnection customer is proposing to
develop a distributed generation facility or modify an existing distributed
generation facility consistent with the interconnection request
application form completed by interconnection customer on
(Date)
; and
Whereas,
interconnection customer desires to
interconnect the distributed generation facility to the EDC's electric
distribution system; and
Whereas,
the EDC has completed an interconnection
feasibility study and provided the results of the study to the interconnection
customer (this recital to be omitted if the Parties have agreed to forego the
interconnection feasibility study); and
Whereas,
the interconnection customer has requested the
EDC to perform an interconnection system impact study to assess the impact of
interconnecting the distributed generation facility to the EDC's electric
distribution system;
Now, therefore,
in consideration of and subject to
the mutual covenants contained in this Agreement the Parties agree as follows:
1. All
terms defined in Section 467.20 of the Illinois Large Distributed Generation
Interconnection Standard shall have the meanings indicated in that Section when
used in this Agreement.
2. The interconnection
customer elects and the EDC shall cause to be performed an interconnection
system impact study consistent with Section 467.70 of the Illinois Large
Distributed Generation Interconnection Standard.
3. The
scope of the interconnection system impact study shall be based upon the
information set forth in the interconnection request application form and in
Attachment A to this Agreement.
4. The
interconnection system impact study shall be based upon the interconnection
feasibility study and the technical information provided by interconnection
customer in the interconnection request application form. The EDC reserves the
right to request additional technical information from interconnection
customer. If the interconnection customer modifies its proposed point of
interconnection or interconnection request, or the technical information
provided in the request is modified, the time to complete the interconnection
system impact study may be extended.
5. The interconnection system impact study report
shall provide the following information:
5.1 Identification
of any equipment short circuit capability limits exceeded as a result of the
interconnection;
5.2 Identification
of any thermal overload or voltage limit violations resulting from the
interconnection;
5.3 Identification
of any instability or inadequately damped response to system disturbances
resulting from the interconnection; and
5.4 Description
and non-binding estimated cost of facilities required to interconnect the
distributed generation facility to EDC's electric distribution system and to
address the identified short circuit, thermal overload, voltage and instability
issues, as required under Section 467.70(e)(2) of the Illinois Large
Distributed Generation Interconnection Standard.
6. The interconnection
customer shall provide a study deposit equal to 100 percent of the estimated
non-binding study costs if the initial application fee deposit has been
depleted. If the initial application fee deposit has been depleted, the study
will not commence until the study deposit has been received by the EDC.
7. The
interconnection system impact study, if required, shall be completed and the
results transmitted to the interconnection customer within 45 business days
after this Agreement is signed by the Parties or the complete study deposit has
been received by the EDC, whichever is later.
8. Study
fees shall be based on actual costs and shall be invoiced to the interconnection
customer after the study is transmitted to the interconnection customer. The
invoice shall include an itemized listing of employee time and costs expended
on the study.
9. The interconnection
customer shall pay any study costs that exceed the deposit within 30 calendar
days after receipt of the invoice. EDC shall refund any excess deposit amount
within 30 calendar days after the invoice.
In witness thereof, the Parties have caused this Agreement
to be duly executed by their duly authorized officers or agents on the day and
year first above written.
[Insert name of interconnection customer]
Signed:
Name (Printed):
Title:
[Insert name of EDC]
Signed:
Name (Printed):
Title:
Attachment A to
Interconnection System Impact Study Agreement
Assumptions Used
in Conducting the Interconnection System Impact Study
The interconnection system impact study shall be based upon
the results of the interconnection feasibility study, subject to any
modifications in accordance with Section 467.70 of the Illinois Distributed
Generation Interconnection Standard, and the following assumptions:
Point of interconnection and configuration to be studied to
the extent it is different from the information provided in the application or
feasibility study.
__________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Note: This
Attachment A is to be completed by mutual agreement of the Parties. Any
additional assumptions (explained below) may be provided by either the
interconnection customer or the EDC.
______________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________