83 Ill. Adm. Code 467.APPENDIX F
F Interconnection Facilities Study Agreement
Section 467.APPENDIX F Interconnection Facilities Study
Agreement
Interconnection
Facilities Study Agreement
This agreement ("Agreement")
is made and entered into this
day of
by and between
("interconnection customer"), as an
individual person, or as a
organized and existing under the
laws of the State of
, and
("Electric Distribution
Company" (EDC)), a
existing under the laws of the
State of Illinois. Interconnection customer and EDC each
may be referred to as a "Party", or collectively as the
"Parties".
Recitals:
Whereas
, the interconnection customer is proposing to
develop a distributed generation facility or modify an existing distributed
generation facility consistent with the interconnection request
application form submitted by the interconnection customer
on
(Date)
; and
Whereas,
the interconnection customer desires to
interconnect the distributed generation facility with the EDC's electric
distribution system; and
Whereas,
the EDC has completed an interconnection
system impact study and provided the results of that study to interconnection
customer; and
Whereas,
the interconnection customer has requested the
EDC to perform an interconnection facilities study to specify and estimate the
cost of the equipment, engineering, procurement and construction work needed to
interconnect the distributed generation facility;
Now, therefore,
in consideration of and subject to
the mutual covenants contained in this Agreement, the Parties agree as follows:
1. All
terms defined in Section 467.20 of the Illinois Large Distributed Generation
Interconnection Standard shall have the meanings indicated in that Section when
used in this Agreement.
2. The interconnection
customer elects and the EDC shall cause an interconnection facilities study
consistent with Section 467.70 of the Illinois Large Distributed Generation
Interconnection Standard.
3. The
scope of the interconnection facilities study shall be determined by the
information provided in Attachment A to this Agreement.
4. An
interconnection facilities study report (1) shall provide a description,
estimated cost of system upgrades, and schedule for required facilities to
interconnect the distributed generation facility to the EDC's electric
distribution system; and (2) shall address all issues identified in the
interconnection system impact study (or identified in this study if the system
impact study is combined with this Agreement).
5. The interconnection
customer shall provide a study deposit equal to 100 percent of the estimated
non-binding study costs if the initial application fee deposit has been
depleted.
6. In
cases in which no system upgrades are required, the interconnection facilities
study shall be completed and the results shall be transmitted to the interconnection
customer within 15 business days after this Agreement is signed by the Parties.
In cases in which system upgrades are required, the interconnection facilities
study shall be completed and the results shall be transmitted to the interconnection
customer within 35 business days after this Agreement is signed by the Parties
or the complete study deposit has been received by the EDC, whichever is later.
The study will not commence until the deposit has been received by the EDC.
7. Study fees
shall be based on actual costs and will be invoiced to the interconnection
customer after the study is transmitted to the interconnection customer. The
invoice shall include an itemized listing of employee time and costs expended
on the study.
8. The interconnection
customer shall pay any actual study costs that exceed the deposit within 30
calendar days after receipt of the invoice. The EDC shall refund any excess
deposit amount within 30 calendar days after the invoice.
In witness whereof, the Parties have caused this Agreement
to be duly executed by their duly authorized officers or agents on the day and
year first above written.
[Insert name of interconnection customer]
Signed:
Name (Printed):
Title:
[Insert name of EDC]
Signed:
Name (Printed):
Title:
Attachment A to
Interconnection Facilities Study Agreement
Minimum Information
that the Interconnection Customer Must Provide
with the
Interconnection Facilities Study Agreement
Provide location plan and simplified one-line diagram of the
distributed generation facilities.
For staged projects, please indicate size and location of
planned additional future generation.
On the one-line diagram, indicate the generation capacity attached
at each metering location. (Maximum load on CT/PT)
On the one-line diagram, indicate the location of auxiliary
power. (Minimum load on CT/PT) Amps
One set of metering is required for each generation
connection to the EDC's electric distribution system.
Number of generation connections:
Will an alternate source of auxiliary power be available
during CT/PT maintenance?
Yes
No
Will a transfer bus on the generation side of the metering
require that each meter set be designed for the total distributed generation
capacity?
Yes
No
(Please indicate on the one-line diagram.)
What type of control system or PLC will be located at the
distributed generation facility?
What protocol does the control system or PLC
use?
Please provide a scale drawing of the site. Indicate the
point of common coupling, distribution line, and property lines.
Number of third party
easements required for EDC's interconnection facilities:
To be completed in coordination with EDC.
Is the distributed generation facility located in EDC's
service area?
Yes
No
If No, please provide name of local provider:
Please provide the following proposed schedule dates:
Begin Construction Date:
Generator Step-up Transformers Receive Back Feed Power Date:
Generation Testing Date:
Commercial Operation Date: