8 Ill. Adm. Code 259.510
General
Section 259
Section 259.510 General
This Section provides for the
issuance of a Notice of Closure following the satisfactory completion of
corrective actions and submittal of a corrective action report.
a) Upon completion of the activities described in the approved
corrective action plan, the owner or operator shall submit a corrective action
report to the Department. The report must provide adequate evidence to
demonstrate that the actions were completed in accordance with the approved
plan and that the cleanup objectives have been attained.
b) The corrective action report shall provide the following:
1) certification, by the facility owner and by the licensed
professional geologist, professional engineer or licensed industrial hygienist
who conducted the site assessments and supervised implementation of the
corrective action plan, that all components of the approved corrective action
plan were fully implemented;
2) facility site maps, at a scale no larger than 1 inch equal to
200 feet, of sufficient detail and accuracy to show all of the following:
A) the boundaries of the facility;
B) any areas of the site from which agrichemical contaminated
soils were removed;
C) any areas of the site on which an engineered barrier was
installed; and
D) the map scale (graphic and nominal), north arrow, date, name
and address of preparer, and location of the site with respect to section,
township, range, and principal meridian;
3) a list of the agrichemicals that were included in the soil or
groundwater remediation activities;
4) documentation of the volume of soil removed from the site and
how the contaminated soil was disposed of;
5) as-built drawings of any engineered barriers constructed to
achieve the approved remediation objectives;
6) copies of any documents describing institutional controls
accompanying engineered barriers;
7) if groundwater remediation activities were conducted, copies
of all analytical results of groundwater monitoring to demonstrate that the
approved groundwater cleanup objectives were attained; and
8) the results of a final inspection by representatives of the
Department or Board.