8 Ill. Adm. Code 900.503
Livestock Waste Handling Facilities Not Subject to the Public Informational Meeting Process
Section 900
Section 900.503 Livestock
Waste Handling Facilities Not Subject to the Public Informational Meeting
Process
For a livestock waste
handling facility
, other than a livestock waste lagoon, that is not subject
to the public informational meeting process as outlined in
Section 12 of the
Livestock Management Facilities
Act
[510 ILCS 77] and Subpart D of this
Part, the following procedures shall be followed:
a) For a new livestock waste handling facility, a site
investigation shall be conducted in accordance with Subpart C of 35 Ill. Adm.
Code 506 to determine whether aquifer material is considered present (or not
present) within 5 feet of the planned bottom of the livestock waste handling
facility, the proposed facility is located in the floodway or flood fringe of a
100-year floodplain, and the proposed facility is located in a karst area or
within 400 feet of a natural depression in a karst area.
A livestock waste
handling facility owner may rely on guidance from the local soil and water
conservation district, the Natural Resources Conservation Service of the United
States Department of Agriculture, or the University of Illinois Cooperative
Extension Service for soil type and associated information.
[510 ILCS
77/13(c)]
b)
A construction plan of the waste handling structure with
design specifications of the structure noted as prepared by or for the owner or
operator shall be filed with the Department at least 10 calendar days prior to
the anticipated dates of construction.
[510 ILCS 77/11(b)] Construction
standards and specifications shall be utilized as set forth in Subpart C of 35
Ill. Adm. Code 506.
c) For a livestock waste handling facility required to conduct a
site investigation pursuant to subsection (a) of this Section, the construction
plan required pursuant to subsection (b) of this Section shall include a
certification statement from the owner or operator on a form provided by the
Department. The statement shall certify that the site investigation meets all
the applicable requirements of subsection (a) of this Section and Subpart C of
35 Ill. Adm. Code 506, and whether aquifer material is considered present (or
not present) within 5 feet of the planned bottom of the livestock waste
handling facility, the proposed facility is located in the floodway or flood
fringe of a 100-year floodplain, and the proposed facility is located in a
karst area or within 400 feet of a natural depression in a karst area. The
statement shall be accompanied by supporting justification, data, and the
results of the site investigation, all from a Licensed Professional Engineer or
Licensed Professional Geologist or by a representative of the Natural Resources
Conservation Service of the United States Department of Agriculture designated
to perform such functions.
d)
Upon receipt of the site investigation information,
if
required,
and construction plan,
the Department shall review the
documents to determine if all information has been submitted or if
clarification is needed. The Department shall, within 15 calendar days
after
receipt of the construction plan, notify the owner or operator that
construction may begin,
if all applicable requirements of the Livestock
Management Facilities Act [510 ILCS 77] and this Part have been met,
or that
clarification is needed.
[510 ILCS 77/11(b)] No later than 15 calendar
days after receipt of the clarification information, the Department shall
notify the owner or operator that construction may begin, if all applicable
requirements of the Livestock Management Facilities Act and this Part have been
met, or that additional clarification is needed.