92 Ill. Adm. Code 530.420
Underground Facilities – Petroleum Products Pipelines
Section 530
Section 530.420 Underground
Facilities – Petroleum Products Pipelines
a) General
1) Petroleum products pipelines are those carrying crude or
refined liquid petroleum products including, but not limited to, gasoline,
distillates, propane, butane, or coal-slurry. Petroleum products pipelines
are, with few exceptions, transmission lines delivering products to processing
or distribution facilities. Petroleum products pipelines installed on State
highway right-of-way shall conform to the applicable sections of ANSI Standard
Code for Pressure Piping which is incorporated by reference in Section 530.20.
(Liquid Petroleum Transportation Piping Systems ANSI-B 31.4)
2) Crossing installation by open trench will be permitted only
prior to roadway construction with vented encasement provided between ultimate
ditch lines or toes of slopes of the highway as a minimum or as directed by the
engineer. No above-ground vent pipes shall be located in the area established
as clear zone for that particular section of highway.
3) Encasement may be eliminated under the following conditions:
A) extra heavy pipe is used; and
B) cathodic protection of the pipe is provided.
4) If encasement is eliminated, maintenance of damaged or decayed
pipe may not disrupt the right-of-way. (See Section 530.30 "Disrupt the
Right-of-Way")
5) The location of petroleum products pipeline crossings shall be
marked at the right-of-way lines with markers that identify the utility and
provide emergency telephone numbers in accordance with current Federal
regulations. (See 49 CFR 192.707 (1989))
b) Fully Access-controlled Highways
1) Longitudinal Petroleum Products Pipelines
New longitudinal petroleum products pipelines will not be
permitted within the access-control lines of fully access-controlled State
highways. Existing longitudinal installations shall be relocated if they
cannot be serviced except from through travel lanes, shoulders, or ramps of the
highway. Longitudinal petroleum products pipelines may be permitted outside
the access-control lines where frontage roads or other corridors provide access
for servicing the facilities.
2) Petroleum Products Pipeline Crossings
Petroleum products pipelines may be permitted to cross fully
access-controlled highways under the following conditions:
A) The design, construction methods and materials shall be those
that can be expected to provide maximum maintenance-free service life.
B) Crossing of completed highway projects shall be installed by
jacking or boring with vented encasement provided between the ditch lines or
toes of slopes of the highway as a minimum or as directed by the engineer. No
above-ground vent pipes shall be located in the area established as clear zone
for that particular section of highway. The crossing may be installed using
tunneling with vented encasement, but only when the installation is not
possible by other means. When tunneling, the venting of the encasement shall
extend to within one foot of the right-of-way line.
C) Locations shall be avoided where rock excavation or deep cuts
would make crossings with proper cover impractical.
c) Conventional Highways
1) Longitudinal Petroleum Products Pipelines
A) Longitudinal petroleum products pipelines may be permitted on
conventional State highways if the materials, construction methods and other
elements are in conformance with the provisions of this Part.
B) Longitudinal petroleum products pipelines shall be located as
near the right-of-way lines as practicable and not more than eight feet from
and parallel to the right-of-way line.
2) Petroleum Products Pipeline Crossings
Petroleum products pipeline crossings may be permitted to
cross conventional highways under the following conditions:
A) The materials, construction methods and other elements are in
conformance with this Part.
B) Crossings shall be installed by jacking or boring under
completed highway projects with vented encasement provided between ditch lines
or toes of slopes of the highway as a minimum or as directed by the engineer.
No above-ground vent pipes shall be located in the area established as clear
zone for that particular section of highway. The crossing may be installed
using tunneling with vented encasement, but only when the installation is not
possible by other means. When tunneling, the venting of the encasement shall
be within one foot of the right-of-way line.