92 Ill. Adm. Code 530.410
Underground Facilities – Gas Transmission Lines
Section 530
Section 530.410 Underground
Facilities – Gas Transmission Lines
a) General
1) Gas pipelines shall be constructed, maintained, and operated
in a Department approved, as defined in Section 530.30, manner and in
conformance with "Transportation of Natural and Other Gas by Pipeline:
Minimum Federal Safety Standards" incorporated by reference at Section
530.20.
2) Crossing installations by open trench will be permitted only
prior to roadway construction with vented encasement provided between ultimate
ditch lines or toes of slopes of the highway as a minimum or as directed by the
engineer. No above-ground vent pipes shall be located in the area established
as clear zone for that particular section of highway.
3) Gas pipeline crossings shall have a minimum cover of 30 inches
at all locations on right-of-way, including below design ditch elevation even
if the ditch is higher than design elevation.
b) Fully Access-controlled Highways
1) Longitudinal Gas Pipelines:
New longitudinal gas pipelines will not be permitted within
the access-control lines of fully access-controlled highways. Existing
longitudinal gas pipelines may be permitted to remain if they can be serviced
without access from the through-travel lanes, shoulders, or ramps of the fully
access-controlled highway.
2) Gas Pipeline Crossings:
Gas transmission and distribution lines may be permitted to
cross fully access-controlled highways under the following conditions:
A) The crossing provides a transmission or distribution service to
a general area or an expanding area. No individual service lines will be
permitted to cross a fully access-controlled highway except in cases of extreme
hardship involving critical needs and isolated locations.
B) The design, materials and construction methods shall be those
that can be expected to provide maximum maintenance-free service life.
C) Crossings under completed highway projects shall be installed
by jacking or boring with vented encasement provided between the ditch lines or
toes of slopes of the highway as a minimum or as directed by the engineer. No
above-ground vent pipes shall be located in the area established as clear zone
for that particular section of highway. The crossing may be installed using
tunneling with vented encasement but only when the installation is not possible
by other means. When tunneling, the venting of the encasement shall extend to
within one foot of the right-of-way line. Crossings may also be installed by
the use of "moles," "whip augers" or other approved methods
which compress the earth to make the opening for pipe.
D) Encasement may be eliminated under the following conditions:
i) extra heavy pipe is used; and
ii) cathodic protection of the pipe is provided.
E) If encasement is eliminated, maintenance of damaged or decayed
pipe may not disrupt the right-of-way. (See Section 530.30 "Disrupt the
right-of-way")
F) Locations shall be avoided where rock excavation or deep cuts
would make crossings with proper cover impractical.
G) The locations of the crossing pipe shall be marked at the
right-of-way line with markers that identify the utility and provide emergency
telephone numbers.
c) Conventional Highways
1) Longitudinal Gas Pipelines:
A) Gas pipelines for transmission, distribution, and service may
be permitted longitudinal to the centerline of conventional State highways if
the materials, construction methods, and other elements are in conformance with
the provisions of this Part.
B) Longitudinal gas transmission lines shall be located as near
the right-of-way line as practicable and not more than eight feet from and
parallel to the right-of-way line.
2) Gas Pipeline Crossings:
Gas pipelines for transmission, distribution, and service may
be permitted to cross conventional State highways under the following
conditions:
A) Crossings of over 60 psig shall be installed by jacking or
boring with vented encasement provided between the ditch lines or toes of
slopes of the highway as a minimum or as directed by the engineer. No
above-ground vent pipes shall be located in the area established as clear zone
for that particular section of highway. The crossing may be installed using
tunneling with vented encasement, but only when the installation is not
possible by other means. When tunneling, the venting of the encasement shall
extend within one foot of the right-of-way line. Crossings may also be
installed by the use of "moles," "whip augers" or other
approved methods which compress the earth to make the opening for the pipe.
B) Encasement will not be required for crossings of 60 psig or
less.
C) Encasement may be eliminated under the following conditions:
i) extra heavy pipe is used; and
ii) cathodic protection of the pipe is provided.
D) If encasement is eliminated, maintenance of damaged or decayed
pipe may not disrupt the right-of-way. (See Section 530.30 "Disrupt the
Right-of-Way")
E) The locations of the crossing pipe for transmission and
distribution lines shall be marked at the right-of-way line with markers that
identify the utility and provide emergency telephone numbers. In urban areas,
the markers for transmission and distribution lines may be eliminated as
provided in current Federal regulations. (See 49 CFR 192.707 (1989))
F) In built-up or expanding areas, frequent service crossings are
discouraged in favor of establishing distribution on both sides of the
highway. The Department reserves the right to reject permits involving
frequent service crossings.