410 IAC 6-10.1-91

410 IAC 6-10.1-91 Elevated sand mound on-site sewage systems: protection of the site

Last amended: 2024Year: 2027Length: 120 wordsOfficial source

Cite as Ind. Admin. Code tit. 410, r. 6-10.1-91

Sec. 91. (a) Before the start of any construction on the property, the following areas must be staked out and protected from disturbance: (1) The soil absorption system area. (2) The dispersal area. (3) The subsurface drainage system area. (4) The set-aside area (if required in the approved plan). (5) Areas designated for future expansion (if required in the approved plan). (b) Special caution shall be taken to prevent wheeled and tracked vehicles from compacting the area selected for placement of the elevated sand mound soil absorption system before, during, and after construction, especially during wet weather. Alteration of soil structure by movement of vehicles may be grounds for rejection of the site or the on-site sewage system, or both.
410 IAC 6-10.1-91: 410 IAC 6-10.1-91 Elevated sand mound on-site sewage systems: protection of the site | Justis AI