25 IAC 2-7-4
25 IAC 2-7-4 Contract letter; documents required to initiate work
Cite as Ind. Admin. Code tit. 25, r. 2-7-4
Sec. 4. The Contract shall be transmitted to the Contractor for his execution by a letter stating that the Contractor unless otherwise instructed
in writing, should not commence any work or take delivery of noninventory materials until he receives a copy of the fully executed contract signed
by all required signatories and all auxiliary documents including but not limited to insurance and bonds are completed and furnished to the state.