327 IAC 8-3.5-3
327 IAC 8-3.5-3 Eligibility and exclusions for eligibility
Cite as Ind. Admin. Code tit. 327, r. 8-3.5-3
Sec. 3. (a) A responsible person as defined by section 6 of this rule is eligible for a general construction permit.
(b) A responsible person, responsible person's engineer, responsible person's developer, or the proposed public water system that has been
issued a general construction permit program ban by the commissioner in accordance with section 8 of this rule is not eligible for a general
construction permit.
(c) Proposed water main projects to a public water system under a connection ban in accordance with 327 IAC 8-3-4.2 are
not eligible for a general construction permit.
(d) Proposed water main projects that meet any of the following criteria are not eligible for a general construction permit as defined by
this rule:
(1) The corresponding public water system has a two (2) year average peak that is between ninety percent (90%) and one hundred
percent (100%) of the public water system's daily capacity, and the product of the following is equal to or exceeds two percent (2%) of the public
water system's daily capacity:
(A) The average daily customer demand of the proposed water main.
(B) The peaking factor of the proposed water main.
(2) The corresponding public water system's two (2) year average peak is equal to or less than ninety percent (90%) of the public water
system's daily capacity and the sum of corresponding public water system's two (2) year average peak, and the product of the following is equal to
or exceeds ninety-two percent (92%) of the public water system's daily capacity:
(A) The average daily customer demand of the proposed water main.
(B) The peaking factor of the proposed water main.
(3) The sum of corresponding public water system's two (2) year average peak and the product of the following is equal to or exceeds
one hundred percent (100%) of the public water system's daily capacity:
(A) The average daily customer demand of the proposed water main.
(B) The peaking factor of the proposed water main.
(e) Proposed projects that meet the definition of a transmission main as defined by section 1 of this rule are not eligible for a general
construction permit.
(f) An individual construction permit issued under 327 IAC 8-3 is required for all other water main extension construction
meeting the criteria of 327 IAC 8-3-2(a) that is not eligible for a general construction permit in accordance with this section or does not