327 IAC 8-4.1-12
327 IAC 8-4.1-12 Submittal requirements for proposed new wells
Cite as Ind. Admin. Code tit. 327, r. 8-4.1-12
Sec. 12. (a) For a proposed well site in a department approved Phase I or Phase II WHPP, with the proposed well included in the WHPA
delineation, the CPWSS shall apply for a construction permit, as provided for in 327 IAC 8-3, and shall describe the proposed well site
in relation to the approved WHPA.
(b) For a proposed well site in a department approved Phase I or Phase II WHPP, with the proposed well not included in the WHPA
delineation, the CPWSS shall apply for a construction permit as provided for in 327 IAC 8-3, and shall submit new well site submittal
requirements as described in section 13 of this rule.
(c) For a proposed well site in a wellfield not in a department approved Phase I or Phase II WHPP, the CPWSS must apply for a
construction permit as provided for in 327 IAC 8-3, and shall submit new well site submittal requirements as described in section 13
of this rule.