329 IAC 11-12-1
329 IAC 11-12-1 Operation approval
Cite as Ind. Admin. Code tit. 329, r. 11-12-1
Sec. 1. (a) A newly constructed solid waste processing facility or incinerator that holds a valid permit under this article must not accept
solid waste until it has complied with the applicable preoperational requirements of this rule.
(b) The operator of the facility shall notify the commissioner in writing when all the applicable preoperational requirements have been
completed. Unless the commissioner denies operational approval within fourteen (14) days of receipt of such notice, the facility may begin to accept
solid waste in accordance with its permit and the applicable operational requirements of 329 IAC 11-7, 329 IAC 11-13,
329 IAC 11-14, 329 IAC 11-15, 329 IAC 11-19, and 329 IAC 11-20.