LAC 43:V.967
LAC 43:V.967. Decommissioning Removal Requirements [Formerly LAC 43:I.1167]
Cite as La. Admin. Code tit. 43, pt. V, § 967
A. The lessee must remove all equipment, including, but not limited to, facilities, turbines, support structures, pipeline, and cables, and shall comply with the decommissioning requirements as set forth by the U.S. Army Corps of Engineers. The lessee shall also comply with any additional or more stringent decommissioning requirements mandated by the board, through OMR.
B. Within 60 days after the removal of a facility, the lessee shall verify to the board, through OMR, that it has removed all equipment required to be removed and that it has cleared the state lands and water bottoms of all obstructions.