301 CMR 11.01
General Provisions
(1) Authority and Purpose.
(a) General. 301 CMR 11.00 is promulgated to create a uniform system for compliance
with the Massachusetts Environmental Policy Act, M.G.L. c. 30, §§ 61 through 62L
(MEPA). The purpose of MEPA and 301 CMR 11.00 is to provide meaningful opportunities
for public review of the potential environmental impacts of Projects for which Agency
Action is required, and to assist each Agency in using (in addition to applying any other
applicable statutory and regulatory standards and requirements) all feasible means to avoid
Damage to the Environment or, to the extent Damage to the Environment cannot be avoided,
to minimize and mitigate Damage to the Environment to the maximum extent practicable.
(b) MEPA Review. MEPA review is an informal administrative process that is intended
to involve any interested Agency or Person as well as the Proponent and each Participating
Agency. The Secretary conducts MEPA review in response to one or more review
documents prepared and filed by a Proponent. The Secretary’s decision that a review
document is adequate or that there has been other due compliance with MEPA and 301 CMR
11.00 means that the Proponent has adequately described and analyzed the Project and its
alternatives, and assessed its potential environmental impacts and mitigation measures. A
Participating Agency retains authority to fulfill its statutory and regulatory obligations in
permitting or reviewing a Project that is subject to MEPA review, which does not itself result
in any formal adjudicative decision approving or disapproving a Project. Consistent with
M.G.L. c. 30, § 62K, the Secretary and all EEA agencies must consider Environmental
Justice Principles in implementing MEPA review. Accordingly, MEPA review shall be
conducted in a manner that provides sufficient disclosures to allow for a full consideration
of Environmental Justice Principles in order to reduce the potential for unfair or inequitable
effects upon Environmental Justice Populations.
(c) MEPA and Agency Actions. MEPA review is intended to inform the Proponent and
each Participating Agency, to maximize consistency between Agency Actions, and to
facilitate coordination of all environmental and development review and permitting processes
of the Commonwealth. It provides an opportunity in one or more review documents for the
Proponent to identify required Agency Actions and describe and analyze how the Project
complies with applicable regulatory standards and requirements. Each Participating Agency
shall review the MEPA submittals and specify any aspects of the Project or issues regarding
its Agency Action that require additional description or analysis (beyond that already
provided in the review documents or any application for a Permit, Financial Assistance, or
a Land Transfer) to enable it to take Agency Action on the Project or fulfill its obligations
in accordance with M.G.L. c. 30, § 61 and M.G.L. c. 30, § 62K. The Secretary may specify
in the certificate on a review document any appropriate consultation by and between the
Proponent and each Participating Agency and may hold informational meetings prior to or
during MEPA review to ensure appropriate consultation.
(Mass. Register #1566, 01/30/2026)
(d) MEPA and Environmental Planning. MEPA review is intended to facilitate
environmental planning for Projects requiring Agency Action, including an Agency's
programs, regulations, or policies. It enables the Proponent and each Participating Agency
to consider the positive and negative, short-term and long-term potential environmental and
public health impacts for all phases of a Project, and the cumulative impacts of the Project
and any other Project or other work or activity in the immediate surroundings and region.
It also enables an Agency to consider the cumulative impacts of Projects requiring individual
Agency Actions taken in accordance with each of its programs, regulations and policies that
may not otherwise be subject to adequate MEPA review or that may have similar
environmental impacts such that a common assessment may be necessary or appropriate.
MEPA review can influence the planning and design of a program, regulations, policy, or
other Project to enable an Agency to achieve these goals, provided that MEPA review is
initiated sufficiently early and in any event prior to the Proponent finalizing or otherwise
irreversibly committing to the program, regulations, policy, or other Project.
(2) Applicability.
(a) Jurisdiction.
1. MEPA establishes jurisdiction over: a Project undertaken by an Agency; those
aspects of a Project within the subject matter of any required Permit; a Project that seeks
the provision of Financial Assistance; and those aspects of a Project within the area of
any Land Transfer. MEPA jurisdiction determines the Scope, if an EIR is required. The
Scope shall enable Agencies to fulfill their obligations under 301 CMR 11.12(5).
2. MEPA jurisdiction is broad when a Project is undertaken by an Agency or seeks the
provision of Financial Assistance. Broad, or full scope, jurisdiction means that the
Scope, if an EIR is required, shall extend to all aspects of a Project that are likely,
directly or indirectly, to cause Damage to the Environment.
3. MEPA jurisdiction is limited when a Project is undertaken by a Person and requires
one or more Permits or involves a Land Transfer, but does not seek the provision of
Financial Assistance. Limited, or subject matter, jurisdiction means that the Scope, if an
EIR is required, shall be limited to those aspects of the Project within the subject matter
of any required Permit or within the area subject to a Land Transfer that are likely,
directly or indirectly, to cause Damage to the Environment. Subject matter jurisdiction
may be functionally equivalent to full scope jurisdiction in the case of a Project, for
example, requiring a Chapter 91 License or involving a Land Transfer of the entire
Project site. Subject matter jurisdiction may be limited to a particular structure, facility
or activity and its direct and indirect environmental impacts in the case of a Project, for
example, requiring a Sewer Extension/Connection Permit or involving a Land Transfer
of a discrete portion of the Project site on which the access roadway is proposed.
(b) Review Thresholds.
1. 301 CMR 11.00 establishes review thresholds that identify categories of Projects or
aspects thereof, of a nature, size or location that are likely, directly or indirectly, to cause
Damage to the Environment. Except when the Secretary requires fail-safe review, the
review thresholds determine whether MEPA review is required.
2. MEPA review is required when one or more review thresholds are met or exceeded
and the subject matter of at least one review threshold is within MEPA jurisdiction. A
review threshold that is met or exceeded specifies whether MEPA review shall consist
of an ENF and a mandatory EIR or of an ENF and other MEPA review if the Secretary
so requires. The subject matter of a review threshold is within MEPA jurisdiction when
there is full-scope jurisdiction (i.e., the Project is undertaken by an Agency or seeks the
provision of Financial Assistance) or when the subject matter of the review threshold is
conceptually or physically related to the subject matter of one or more required Permits
(provided that the review thresholds for Land and Areas of Critical Environmental
Concern shall be considered to be related to the subject matter of any required Permit)
or the area subject to a Land Transfer.
3. The review thresholds do not apply to: a lawfully existing structure, facility or
activity; Routine Maintenance; a Replacement Project; any Project consisting solely of
one single family dwelling or multifamily housing of up to 50 dwelling units for which
the only required Agency Action is a Superseding Order of Conditions from the
Massachusetts Department of Environmental Protection; or a Project that is consistent
with a Special Review Procedure review document, or other plan or document that has
been prepared with the express purpose of assessing the potential environmental impacts
from future Projects, has been reviewed as such in accordance with MEPA and 301 CMR
11.00, and has been allowed or approved by any Participating Agency, unless the filing
of an ENF and an EIR was required by a decision of the Secretary on any such review
document, plan or document.
4. Any Project seeking to qualify in its entirety as an Ecological Restoration Project, but
not including an Ecological Restoration Limited Project under 310 CMR 10.24(8) and
10.53(4), shall not be required to undergo MEPA review, provided the requirements of
301 CMR 11.01(2)(b)4. are met. At least 60 days prior to filing a Notice of Intent for a
Restoration Order of Conditions, the Proponent shall submit a Notice of Project with the
MEPA Office for publication in the Environmental Monitor. Said Notice of Project shall
include, in a format prescribed by the Secretary, a scope of work for the proposed
restoration activities, an estimate of the nature and extent of wetlands alteration, and a
statement that the Project will meet the eligibility criteria for a Restoration Order of
Conditions under 310 CMR 10.13: Eligibility Criteria for Restoration Order of
Conditions for an Ecological Restoration Project, but not including an Ecological
Restoration Limited Project under 310 CMR 10.24(8) and 10.53(4), together with
identification of the project type and a list of the documentation that will be provided to
the issuing authority. Any Project that is located within a Designated Geographic Area
around one or more Environmental Justice Populations shall also comply with 301 CMR
11.05(4), and shall include in the Notice of Project a description of measures taken to
enhance public involvement opportunities by the identified Environmental Justice
Populations, and a description of anyEnvironmental Burdens or Environmental Benefits
that may result for the Environmental Justice Populations by reason of the Project.
Advance notification shall be provided in accordance with 301 CMR 11.05(4)(b) no later
than 45 Days, and no earlier than 90 Days, prior to submitting the Notice of Project to
the MEPA Office for publication. Comments on the Notice of Project shall be received
for 20 Days following publication of the notice, and unless the Secretary issues a
determination within ten Days after the close of the comment period indicating that the
Project requires an ENF filing, any Agency Action required for the Project may be taken
if required to obtain a Restoration Order of Conditions, provided that the Agency Action
shall be deemed to be conditioned on the ultimate issuance of the Restoration Order of
Conditions. If the Restoration Order of Conditions for an Ecological Restoration Project
is denied, a Project that requires Agency Action and meets or exceeds one or more
MEPA review thresholds must thereafter undergo MEPA review, and any conditional
Agency Action taken in accordance with 301 CMR 11.01(2)(b)4. shall not become
effective until MEPA review is completed. Consistent with 301 CMR 11.12(6), the
Agency may reconsider the Agency Action and any conditions thereof following the
completion of MEPA review.
(c) The following categories of Projects shall not be presumed likely or reasonably likely
to cause Damage to the Environment, notwithstanding that the Project exceeds one or more
review thresholds in 301 CMR 11.03, provided an ENF is filed in accordance with 301 CMR
11.01(2). The Secretary, after review of the ENF, shall issue a written certificate in
accordance with 301 CMR 11.06(7)(a).
1. Any Project satisfying all of the criteria in 301 CMR 11.01(2)(c)1.a. through g.:
a. devotes 67% or more of the gross floor area of the Project to residential uses, with
the remainder devoted to supportive commercial, cultural, educational, community
and/or civic uses. For the purpose of this 301 CMR 11.01(2)(c)1.a., gross floor area
shall not include parking, utility space, and other ancillary spaces not intended for
exclusive occupancy by the user or tenant;
b. achieves density of at least eight units per acre for single-family, at least 12 units
per acre for two and three family buildings, and at least 15 units per acre for
multi-family housing of more than three-family residential uses;
c. alters up to five acres of previously undeveloped land; or alters up to ten acres of
previously undeveloped land and the Project proposes a tree retention and replanting
plan that demonstrates measures to minimize tree removal and replace removed trees
to the maximum extent practicable. To satisfy this 301 CMR 11.01(2)(c)1.c., no
portion of the Project site shall include any land where projected total ecosystem
carbon stocks are in the top quintile statewide, as defined bythe Massachusetts Forest
Carbon Top Quintile data layer issued by EEA; any designated priority habitat, as
defined in 321 CMR 10.02: Definitions and Abbreviations; or any land with soils
classified as prime farmland by the United States Department of Agriculture which
is currently in active agricultural use or was in active agricultural use within the past
five years. Redevelopment of previously developed land, or redevelopment of land
of land within or appurtenant to an office or industrial park or large institutional
property, shall not be defined as alteration of previously undeveloped land for
purposes of this 301 CMR 11.01(2)(c)1.c.
d. the Project site is located outside of highest hazard areas and outside the Special
Flood Hazard Area as defined by the Wetlands Protection Act regulations at 310 CMR
10.00: Massachusetts Endangered Species Act Regulations; or for a redevelopment
Project, the Project site is located outside of highest hazard areas and complies with the
American Society of Civil Engineers Guidance on Structural Safety in Flood Areas
(ASCE 24-24). For the purposes of 301 CMR 11.01(2)(c)1.d., highest hazard areas shall
be those areas subject to high erosion or with exposure to flooding characterized by
factors such as high-velocity flows, high-velocity wave action, breaking wave heights,
sheet flow and scour and flash flooding. Such highest hazard areas shall include, but not
be limited to, the following areas as defined by the Federal Emergency Management
Agency: V, Coastal A and AO zones on a Flood Insurance Rate Map (FIRM) and
floodways and A zones along the banks of waterbodies. The Secretary shall set forth in
guidance methodology for delineating highest hazard areas. For the purposes of
301 CMR 11.01(2)(c)1.d., redevelopment means replacement, rehabilitation, or
expansion of existing structures, improvement of existing roads or reuse of degraded or
previously developed areas.
e.
complies with the Massachusetts Stretch Energy Code adopted pursuant to
St. 2008, c. 169;
f. does not require approval of a new interbasin transfer of water or wastewater,
unless determined to be insignificant by the Water Resources Commission pursuant
to the Interbasin Transfer Act and implementing regulations at 313 CMR
4.00: Interbasin Transfer, and does not require new or expanded gas mains; and
g. generates fewer than 3,000 New adt of traffic on roadways providing access to
a single location; or generates fewer than 6,000 New adt of traffic on roadways
providing access to a single location if the Project is located within one-half mile of
a public transit stop with an existing or proposed safe and accessible path of travel
to the Project site. Projects with 3,000 or more New adt, prior to filing the ENF,
must consult with the Massachusetts Department of Transportation and with the
Massachusetts Bay Transportation Authority or applicable local or regional transit
authority established pursuant to M.G.L. c. 161B, § 3 or § 14.
2. Any Project that does not meet or exceed any mandatory EIR threshold in 301 CMR
11.03, provided the Project satisfies the criteria in 301 CMR 11.01(2)(c)1.a., d., e., and
either 11.01(2)(c)1.b. or 11.01(2)(c)1.c. For the purposes of 301 CMR 11.01(2)(c)2., a
redevelopment Project located in the highest hazard areas, as defined in 301 CMR
11.01(2)(c)1.d., shall be deemed to satisfy the criterion in 301 CMR 11.01(2)(c)1.d. if
the Project complies with the American Society of Civil Engineers Guidance on
Structural Safety in Flood Areas (ASCE 24-24) and demonstrates the absence of off-site
flood impacts on adjacent properties and infrastructure.
3. Any Project that does not meet or exceed any mandatory EIR threshold in 301 CMR
11.03 and seeks to qualify as an Ecological Restoration Limited Project under 310 CMR
10.24(8) and 10.53(4), but does not qualify as an Ecological Restoration Project eligible
for the procedures in 301 CMR 11.01(2)(b)4.
4. Any Project that meets or exceeds any review threshold in 301 CMR 11.03(12),
provided that the Project does not independently propose any work, project or activity
that exceeds any other review threshold in 301 CMR 11.03(1) through (11).
(d) Segmentation. In determining whether a Project is subject to MEPA jurisdiction or
meets or exceeds any review thresholds, and during MEPA review, the Proponent, any
Participating Agency, and the Secretary shall consider the entirety of the Project, including
any likely future Expansion, and not separate phases or segments thereof. The Proponent
may not phase or segment a Project to evade, defer or curtail MEPA review. The Proponent,
any Participating Agency, and the Secretary shall consider all circumstances as to whether
various work or activities constitute one Project including, but not limited to, whether the
work or activities, taken together, comprise a common plan or independent undertakings,
regardless of whether there is more than one Proponent; any time interval between the work
or activities; and whether the environmental impacts caused by the work or activities are
separable or cumulative. Examples of work or activities that constitute one Project include
work or activities that:
1. meet or exceed one or more review thresholds on an area previously subject to a Land
Transfer, provided that not more than five years have elapsed between the Land Transfer
and the work or activities; and
2. construct more than one structure (such as more than one single family dwelling) and
appurtenant structures, facilities, and other improvements on a site, unless a plan for the
subdivision or other legal division creating or allowing separate lots or parcels was
definitively approved or endorsed in accordance with applicable statutes and regulations
prior to the effective date of 301 CMR 11.00.
(3) Relation to Other Authority.
(a) Information regarding Other Authority. The Secretary may require a Proponent to
provide information regarding a Project’s consistency or compliance with any applicable
Federal, municipal, or regional statutes and regulations. MEPA and 301 CMR 11.00 do not
give the Secretary authority to make any formal determination regarding such consistency
or compliance.
(b) Applicability of Other Authority. MEPA and 301 CMR 11.00 do not alter the review
or permitting authority of any Agency or any Federal, municipal, or regional governmental
entity over, or otherwise alter the applicability of any statutes and regulations to, a Project.
(4) General Procedure.
(a) ENF. If a Project is subject to MEPA jurisdiction and either it meets or exceeds one or
more review thresholds or the Secretary requires fail-safe review, the Proponent begins
MEPA review by preparing and filing an ENF with the Secretary. The Secretary publishes
the appropriate pages of the ENF in the next Environmental Monitor. A 30-Day review
period follows, during the first 20 Days of which Agencies, Persons, the MEPA Office
(which ordinarily conducts a site visit and public consultation session), and the Secretary
review and/or comment on the ENF. At the close of the review period for an ENF, the
Secretary decides whether to require an EIR. If the Secretary does not require an EIR, an
Agency may take Agency Action on the Project (see 301 CMR 11.05 and 11.06).
(b) EIR. If the Secretary requires an EIR, the Proponent prepares and files it with the
Secretary. The Secretaryshall ordinarilyrequire a draft and final EIR, but mayallow a single
or rollover EIR. The Secretary publishes notice of the availability of the EIR in the next
Environmental Monitor. A 37-Day review period follows, during the first 30 Days of which
Agencies, Persons, the MEPA Office, and the Secretary review and/or comment on the EIR.
At the close of the review period, the Secretary decides whether the EIR is adequate, and
must consider Environmental Justice Principles in making this determination. An Agency
may take Agency Action on the Project, provided that the Secretary has determined that the
single or final EIR is adequate and 60 Days have elapsed following the publication of the
notice of the availability of the single or final EIR in the Environmental Monitor (see
301 CMR 11.07 and 11.08).
(c) Section 61 Findings. An Agency that takes Agency Action on a Project for which the
Secretary required an EIR:
1. issues Section 61 Findings that specify, based on the EIR, all feasible means to be
used to avoid Damage to the Environment, or, to the extent Damage to the Environment
cannot be avoided, to minimize and mitigate Damage to the Environment to the
maximum extent practicable;
2. if applicable, includes in its Section 61 Findings any and all actions to be taken to
reduce the potential for unfair or inequitable effects upon Environmental Justice
Populations;
3. makes its Section 61 Findings part of the Permit or other document allowing or
approving the Agency Action; and
4. files a copy of its Section 61 Findings with the MEPA Office (see 301 CMR11.12(5)).
(5) Administration.
(a) Authority of Assistant Secretary. The staff of the Secretary that carries out day-to-day
administration of MEPA and 301 CMR 11.00 is organized as the MEPA Office, under the
direction of the Assistant Secretaryof Energy and Environmental Affairs, who is also known
as the MEPA Director. The Secretary may delegate to the Assistant Secretary any of the
Secretary's authorityin accordance with MEPA and 301 CMR 11.00 that the Secretarydeems
appropriate. Any certificate, determination, or other document executed by the Assistant
Secretary in accordance with the delegation shall be deemed the valid and duly authorized
certificate, determination, or other document of the Secretary.
(b) Responsibilities of MEPA Office. The MEPA Office is responsible for: responding to
inquiries from Proponents and other Agencies and Persons; reviewing documents filed in
accordance with MEPA and 301 CMR 11.00; conducting site visits and public consultation
sessions; ensuring adequate prior public notice of site visits, public consultation sessions, and
comment periods, and meaningful opportunities for public review of review documents;
coordinating with any Agency that expects to take Agency Action on a Project; preparing
drafts of certificates, determinations, and other documents for the Secretary; and maintaining
publicly accessible files that contain the complete administrative record on which the
Secretary's decisions in certificates, determinations, and other documents are based.
(6) Advisory Opinion.
(a) Request for Advisory Opinion. In case of doubt as to the meaning or applicability of any
provision or requirement in MEPA or 301 CMR 11.00 (including whether an entity is an
Agency, whether a decision or action is Agency Action, whether a Project is subject to
MEPA jurisdiction, or whether a Project meets or exceeds one or more review thresholds)
an Agency or Person may request an advisory opinion of the Secretary in accordance with
M.G.L. c. 30A, § 8, and 301 CMR 11.00.
(b) Decision on AdvisoryOpinion. The Secretaryshall respond within 20 Days of receiving
a request for an advisory opinion either with a request for further information or with the
advisory opinion, unless the Secretary publishes notice of the request in accordance with
301 CMR 11.01(6)(c). If the Secretary requests further information, the Secretary shall
provide the advisory opinion 20 Days of receiving the requested information.
(c) Public Comment on a Request for an Advisory Opinion. In the case of a request for an
advisory opinion concerning Routine Maintenance or a Replacement Project, the Secretary
shall, and in all other cases, the Secretary may: publish notice of the request in the next
Environmental Monitor and receive into the record, within 20 Days following publication
of the notice of the request (unless extended by the Secretary with the consent of the
Proponent), written comments from any Agency or Person concerning the request. The
Secretary shall provide the advisory opinion within 20 Days after the close of the comment
period.