310 CMR 19.104
Landfill Facility Plan
(1) General. In addition to the general application requirements established in 310 CMR 19.001
through 19.099, 310 CMR 19.030: Application for a Solid Waste Management Facility Permit,
an application for a landfill permit shall include the following components:
(a) landfill site plan;
(b) hydrogeological study;
(c) landfill design plan;
(d) landfill operation and maintenance plan; and
(e) conceptual landfill closure/post-closure plan.
(2) Landfill Site Plan. The landfill site plan shall include:
(a) the locations of permanent on-site bench marks used as a reference point or plane;
(b) the acreage and boundaries of the site, the boundaries of the landfilling operations and
designation of other land uses within the site;
(c) the location and elevations of all proposed and existing environmental monitoring
devices;
(d) the location of all proposed and existing soil borings, excavations and test pits;
(e) the location of all proposed and existing on-site borrow sources;
(f) the location of all proposed and existing utilities, structures and roads;
(g) the distance to any airport runway if less than 10,000 feet;
(h) all Areas of Critical Environmental Concern as determined by the Executive Office of
Environmental Affairs (EOEA), where applicable; and
(i) other information concerning the site which the Department may require for review of
plans.
(3) Hydrogeological Study. A hydrogeological study shall provide the data, maps,
cross-sections, schematics and numerical parameters which the Department reasonably deems
necessary to accurately determine the physical and chemical characteristics of the overburden
material and bedrock present at the site, the directions, pathways and velocities of ground and
surface water flows and the physical and chemical characteristics of the ground and surface
waters.
(a) Submission of a Scope of Work for a Hydrogeological Study.
1. The applicant shall submit the proposed scope of work for a hydrogeological study
to the Department not less than 60 days prior to the commencement of the
hydrogeological study.
2. The applicant shall incorporate all Departmental modifications, additions, changes
or deletions into the final scope of work for the hydrogeological study.
(b) The hydrogeological study shall include without limitation:
1. a narrative summary of the regional and local geological and hydrogeological setting
including a brief description of the major geological formations present (bedrock and
overburden);
2. a description of the general geomorphology of the site;
3. a summary of all relevant environmental and geological studies that have been
performed at the site;
4. a set of maps that depict:
a. the topography of the site;
b. the areal extent of the overburden and/or bedrock on the site, together with
appropriate cross-sections to provide a three-dimensional picture of the site;
c. within a ½ mile of the proposed area of waste deposition, the location of:
i. all water supply wells;
ii. all aquifer and/or groundwater protection zones including Zone II's and/or
Interim Wellhead Protection Areas;
iii. all water sheds and their associated drainage patterns; and
iv. all surface water bodies (indicate designated classifications).
d. within 500 feet of the perimeter of the site, the location of:
i. all wetlands; and
ii. 100 year flood plains.
e. all environmental monitoring points, test borings, test pits, and piezometers on
the site;
f. ground water contours, piezometric heads, hydraulic gradients (horizontal and
vertical), and ground water flow directions, together with the appropriate
cross-sections to provide a three dimensional picture of the site for both the seasonal
high and low ground water periods.
5. sufficient data and information to adequately describe:
a. the physical and chemical characteristics of the major overburden units and
bedrock formations present on the site;
b. the hydraulic connection between the major overburden units and the overburden
units that are in contact with bedrock and the bedrock;
c. the hydraulic conductivity of all major overburden units on the site;
d. the nature and characteristics of any hydrogeologic boundary that exists on the
site;
e. the maximum ground water fluctuations and maximum high ground water level
of the ground water elevation measurement locations;
f. sufficient precipitation data to enable a calculation of the maximum ground water
high;
g. the as-built design of all monitoring wells and piezometers;
h. grain size gradation curves for the overburden material in which the screened
interval of a monitoring well resides;
i. the existing and/or background quality of the ground and surface waters on the
site as regulated in 310 CMR 19.132(1); and
j. the hydrogeologic flow conditions.
6. the following information, if it is determined that there is a component of ground
water flow from the overburden into the bedrock:
a. a bedrock contour map;
b. a fracture trace analysis; and
c. the hydraulic conductivity of the bedrock.
7. a clear and concise presentation of any form of geophysical methods used during field
investigations of the site; and
8. a clear and concise presentation of any computer model that is utilized in the
investigation.
(4) Landfill Design Plan. The landfill design plan shall include:
(a) a ground water protection system design plan which details the configuration of the liner
system, leachate collection system(s), leachate pumping, storage, treatment and disposal
systems, and efficiency of the liner in terms of leachate removal;
(b) schematic drawings, maps and/or plans which delineate in plane view and in detailed
cross-sectional view (at initial, interim and final phases) the elevations of the proposed
landfill, excavations, berms, dikes, ditches, liners, leachate collection system, swales, storm
water detention systems or other drainage features;
(c) design and construction specifications of the landfill, including, but not limited to the
ground water protection system, the environmental monitoring systems, the cap and final
cover, recycling and composting operations and other appurtenances associated with the
facility;
(d) a construction plan that includes a description of the installation methods and
procedures for construction of the liner, leachate collection system, monitoring systems and
other parts of the facility including materials required and scheduling of construction events
and phases;
(e) a quality assurance, quality control (QA/QC) plan for the construction of the landfill
including the ground water protection system, the environmental monitoring systems, the cap
and final cover and other appurtenances associated with the facility. The QA/QC plan shall
specify the qualifications of the QA/QC officers, the qualifications of the installers of the
ground water protection systems and specify the testing and monitoring protocols which shall
form the basis of the engineering certification that the facility was built according to the
approved specifications. The plan shall provide a description of the criteria to be utilized in
detecting and evaluating deficiencies, selecting corrective action methodology and
implementing corrective measures to achieve conformity with the approved plans; and
(f) the location and design of convenience and recycling drop-off areas, if applicable.
(5) Landfill Operation and Maintenance Plan. The landfill operation and maintenance plan
shall include:
(a) a narrative description, with appropriate references to operation and maintenance
requirements specified under 310 CMR 19.130, the site and design plans, of the solid waste
landfill activities proposed to be conducted during the life of the landfill, including the
sequence and direction of cell, lift and phase development; capacity and life expectancy for
each phase; and the sequence of placement of interim and final cover;
(b) a plan for compliance with wastes banned pursuant to 310 CMR 19.017: Waste Bans;
(c) a leachate management plan;
(d) a staffing plan;
(e) an inspection and maintenance plan that includes a proposed schedule for regular
inspections and maintenance of the landfill, including standard operating procedures for:
1. the leachate collection, handling, treatment and disposal system; and
2. landfill equipment.
(f) a facility safety plan, including:
1. a fire control plan developed in conjunction with and certified by the local fire
department or independent licensed fire consultant, including a contingency plan for
containing and suppressing a landfill fire anywhere on the site;
2. a hazardous waste contingency plan for inspecting loads of solid waste and handling
and ensuring that any regulated hazardous wastes are properly transported off-site and
disposed at hazardous waste facilities; and
(g) an environmental monitoring plan that includes:
1. a surface and ground water sampling and analysis plan, based upon the results of the
hydrogeological study specified in 310 CMR 19.105(4), which will ensure the accurate
representation of surface and ground water quality at the upgradient and downgradient
sampling points. At a minimum, this plan shall address:
a. sample collection;
b. sample preservation and shipment;
c. analytical procedures;
d. chain of custody control; and
e. sample collection and analytical QA/QC.
2. an air monitoring plan which establishes the frequency and extent of sampling and
analysis for explosive gasses and air quality; and
(h) other information concerning the operation and maintenance of the facility which the
Department may require for review of plans.
(6) Conceptual Landfill Closure/Post-Closure Plans. The conceptual landfill closure/post-
closure plan shall include:
(a) a narrative description, with appropriate references to the site and design plans, of the
activities necessary to close the landfill pursuant to 310 CMR 19.140 at any point during its
operating life including the site preparation and closure activities necessary to cap and secure
the landfill and activities necessary to maintain and monitor the landfill during the 30 year
post-closure period defined at 310 CMR 19.142(2);
(b) closure and post closure estimates pursuant to 310 CMR 19.051(5): Financial
Assurance Requirements.