310 CMR 19.105
Equivalency Review Standards and Procedures, may approve, in writing, the
use of synthetic covers or other alternatives if such materials provide equivalent or
greater protection than the materials listed in 310 CMR 19.130(15)(c)3.a.
(e) Final Cover.
1. The application of final cover, or alternate in accordance with 310 CMR 19.112,
19.113 or 19.114, shall begin to be applied to a section of the landfill as soon as possible,
but no later than 90 days, or other schedule as approved by the Department, after the
circumstances specified in 310 CMR 19.130(15)(e)1.a. and b. When greater than 30 days
of the 90 day period falls between November 1 and March 1 , final cover shall begin to
st
st
be applied no later than the following April 1 .
st
a. Active landfills:
i. whenever a new lift has not or will not be applied within a one year period
unless the area is permitted to accept additional waste;
ii. upon reaching final approved elevations;
iii. whenever a phase of the landfill has been completed; or
iv. whenever the permit expires or terminates for any reason, or is revoked.
b. Inactive landfills:
i. in accordance with schedules established pursuant to 310 CMR 19.150,
Landfill Assessment Requirements, and 310 CMR 19.151: Corrective Action
Requirements.
2. The final cover shall be designed and constructed in accordance with the
requirements established in 310 CMR 19.112, 19.113 or 19.114.
3. Final cover shall be maintained to prevent erosion and ensure the integrity of the cap.
(f) Maintenance of Intermediate or Final Cover.
1. The final cover system shall be repaired immediately upon the detection of any
failure which may result in the release of pollutants to the environment and shall be
maintained and repaired during the active life of the landfill, the closure period and the
post-closure period.
2. Operators shall repair the intermediate cover, including cover vegetation if used, of
all areas on which intermediate cover has been applied.
(16) Vector, Dust and Odor Control.
(a) The operator shall prevent vectors, dust, odors and other nuisance conditions from
developing at the landfill and any other areas related to the general facility operations.
(b) No pesticides shall be utilized at the landfill except:
1. under the direct supervision of a pesticide operator licensed by the Massachusetts
Department of Food and Agriculture; and
2. upon written notification to the appropriate Department Regional Office and board
of health of such application.
(c) Water shall not be used for dust control in amounts which produce excessive infiltration,
ponding or erosion.
(17) Litter Control.
(a) Landfill operations shall be conducted so as to minimize blowing litter.
(b) The operator shall incorporate litter fencing, natural barriers or other devices to prevent
the scattering of solid waste beyond the working area.
(c) The operator shall maintain the general cleanliness of the facility and surrounding areas
impacted by blown litter from the facility or the access roads.
(18) Top Slope and Side Slopes.
(a) The operator shall ensure that the final top slope has a minimum grade of 5%.
(b) The operator shall ensure that no top slope or side slope grade shall result in excessive
erosion.
(c) The operator shall ensure that final exterior side slopes shall not exceed a slope of three
horizontal to one vertical (3:1).
(d) The operator shall ensure that in no case shall an unstable slope be created or a slope
that could result in abnormal stress on the liner system.
(19) Storm Water Drainage.
(a) The operator shall provide sufficient storm water drainage controls and diversion
structures, channels or ditches to promote drainage off of the landfill, minimize run-on onto
the landfill, prevent uncontrolled ponding on the landfill or uncontrolled ponding adjacent
to the filled area.
(b) Storm water drainage structures shall be designed, constructed and maintained so as to
ensure integrity of the drainage structures and so as to prevent erosion of the landfill.
(20) Erosion Control.
(a) The operator shall institute such soil erosion control measures as are necessary to ensure
the retention and integrity of the daily, intermediate or final cover.
(b) The operator shall ensure that no solid waste or leachate are carried off-site due to
erosion.
(c) The operator shall ensure that siltation due to erosion shall not migrate off-site.
(d) In a situation where significant settlement, uncontrolled ponding of waters or erosion
of the landfill or cover material placed over the landfill occurs during the operation, closure
or the post-closure period the operator or owner shall immediately institute corrective
measures.
(21) Boundary and Elevation Markers.
(a) The operator shall establish and maintain boundary markers at the outermost boundaries
of waste deposition and at the property boundaries. Markers shall, at a minimum, be
established at every change in direction of the boundary.
(b) The operator shall establish and maintain at least one reference elevation marker on an
area of the site that does not contain solid waste.
(22) Access Roads. The access roads shall be constructed, graded and maintained to ensure that
traffic flow will not be interrupted by inclement weather or traffic patterns.
(23) Security.
(a) The operator shall provide sufficient fences or other barriers to prevent access to the
facility except at designated points of entry or exit.
(b) A gate shall be provided at all access points and shall be locked at all times when the
operator or his agent is not on site or during hours when the facility is not operating.
(24) Posting of the Landfill.
The operator of a landfill shall post signs at all access points to the landfill which, at
minimum, include the following information:
(a) the name of the owner and operator of the facility;
(b) a 24 hour emergency telephone number for the facility;
(c) the hours of operation;
(d) a list of solid wastes banned or restricted pursuant to 310 CMR 19.017;
(e) other limitations and conditions of access to the facility; and
(f) penalties for unauthorized use.
(25) Open Burning. The operator shall not cause, suffer, allow or permit the open burning of
any combustible material at the facility except as may be expressly permitted by the Department
pursuant to 310 CMR 7.07: U Open Burning.
(26) Fire Protection and Control.
(a) The operator shall ensure that no materials are stored, held, maintained or placed at a
landfill in such a manner as to pose a fire hazard.
(b) A separate area shall be provided, located away from combustible materials, uncovered
refuse and buildings, for quick dumping and quenching or snuffing of hot loads.
(c) The operator shall immediately notify the fire departments having jurisdiction, and the
appropriate Regional Office of the Department whenever smoldering, smoking or burning
has occurred or is occurring at the landfill.
(d) The operator shall be responsible for seeking fire-fighting assistance, initiating and
providing assistance and/or resources for fire-fighting actions until all smoldering, smoking
and burning cease.
(e) The operator shall not conduct disposal activities in the vicinity of any smoldering,
smoking or burning area. Precautions shall be taken to prevent disposal activities from
interfering with fire-fighting activities.
(f) Any disruption of the finished grade or covered surfaces as a result of fire fighting
activities shall be repaired or replaced immediately upon termination of fire-fighting
activities.
(27) Convenience and Recycling Drop-off Areas at landfills.
(a) The operator may provide one or more containers of sufficient capacity within a
designated secure area under the landfill's control and with the approval of the Department
either for the unloading of solid wastes from private vehicles prior to transport of the solid
waste to the active area of the landfill (convenience areas), or for the collection and
temporary storage of recyclable materials.
(b) Convenience areas and recycling drop-off areas shall be operated in an orderly, safe and
environmentally sound manner.
(c) The convenience or recycling drop-off area shall be located a safe distance from the
active working face and the movement of associated landfill equipment and commercial
vehicles.
(d) The convenience or recycling drop-off area shall be maintained so as to prevent
nuisance conditions from developing and to ensure the sanitary condition and orderly
appearance of the areas.
(e) Solid waste shall be removed from the containers used in the convenience area and
deposited in the working face at such frequency so as not to exceed the capacity of the
containers. The containers shall be emptied, at a minimum, at the end of each day of
operations.
(f) Containers provided for the collection and storage of recyclable materials for transport
off-site shall be emptied whenever filled or every 60 days, whichever is less, or as otherwise
determined by the Department.
(28) Waste Oil Collection at Landfills. Waste oil other than the waste oil generated by the
operator during normal maintenance of equipment used on-site may be collected and stored at
landfills only with the approval of the Department.
(29) Household Hazardous Waste Collections at Landfills. Household hazardous waste shall
be collected at landfills only with the approval of the Department and consistent with 310 CMR
30.000: Hazardous Waste.
(30) Leachate Collection, Treatment and Disposal.
(a) Leachate shall be collected, stored, handled, treated on or off-site and disposed in
accordance with approved plans and the permit.
(b) The storage of leachate should not exceed one foot of hydraulic head on the liner except
during storm events and be designed to drop below one foot within seven days of a 25-year
storm for the primary operational phase of the landfill.
(c) Leachate shall not be discharged directly to waters of the Commonwealth except in
accordance with a discharge permit issued by the Department pursuant to 314 CMR 5.00
Ground Water Discharge Permit Program or 314 CMR 7.00: Sewer System Extension and
Connection Permit Program.
(d) Leachate shall not be discharged to a sewer except in accordance with a sewer
connection permit issued pursuant to 314 CMR 12.00.
(e) Leachate shall only be stored at the landfill pursuant to the requirements of 314 CMR
18.00: Industrial Wastewater Holding Tank and Container Construction, Operation, and
Record Keeping Requirements.
(f) Leachate shall be removed from a landfill leachate storage facility for off-site treatment
or disposal only by a licensed liquid waste hauler and only when there is a contractual or
otherwise appropriate guarantee for disposal of the leachate.
(g) The operator shall have contracts or otherwise appropriate plans for back-up handling,
treatment and disposal for leachate expected to be generated by the landfill in the case of
interrupted service of the primary handling, treatment and disposal option.
(h) Inspection reports, as required under 310 CMR 19.130(35), shall include the quantity
of leachate generated, the leachate disposal location, results of leachate tank testing and
monitoring and other routine maintenance performed.
(i) Leachate collection, storage, treatment, and disposal shall continue during the entire
active life of the landfill, and during the closure and the post-closure periods.
(31) Phase Completion of the Landfill.
(a) Landfill operations shall be conducted in phases in accordance with approved plans to
reduce the amount of active area exposed.
(b) Final cover shall be placed on completed phases and shall be maintained to prevent
erosion and ensure the integrity of the cap.
(c) Construction of the Final Cover. Construction of the final cover shall consist of the
construction of the final cover and all associated appurtenances. Construction of the final
cover shall be carried out in conformance with 310 CMR 19.107: Construction
Certification. The independent professional engineer shall:
1. notify the Department in writing two weeks prior to the start of construction of the
low permeability cap;
2. ensure that:
a. the completed phase is graded in a manner that facilitates surface drainage and
is consistent with the surrounding topography;
b. the completed phase is completely covered by a final cover in accordance with
310 CMR 19.112;
c. the construction of the final cover does not in any way interfere with proper
drainage of adjacent lands or concentrate run-off waters on adjacent areas;
d. the phase has an air quality protection system designed and constructed in
accordance with 310 CMR 19.117; and
e. the phase has an operative environmental monitoring system designed and
implemented in accordance with 310 CMR 19.118.
3. notify the Department in writing two weeks prior to the completion of construction
of the final cover; and
4. submit a copy of the engineer's certification to the Department.
(d) Letter of Compliance.
1. Following receipt of the engineer's certification specified at 310 CMR
19.130(31)(c)4. the Department shall inspect the landfill and shall:
a. issue a letter of compliance certifying that the landfill or phase thereof has
received final cover in accordance with approved plans; or
b. issue a letter citing deficiencies and requiring corrective action.
(32) Disruption of Landfilled Areas.
(a) No person shall excavate, disrupt or remove deposited material from either an active,
inactive or closed landfill without prior written approval from the department.
(b) All requests for approval shall include a plan describing the area involved, depth of such
excavated material, where material is to be re-deposited and estimated time required for
completion of excavation procedures.
(c) All excavations shall be confined to an area consistent with the number of pieces of
digging equipment and/or trucks used for haulage.
(d) Adequate measures shall be taken during excavation to control dust, odors, fires,
potential for release of gas and explosions, rodents, insects and blowing litter.
(e) The re-deposition of all excavated solid wastes shall be in conformity with all
requirements of 310 CMR 19.000.
(33) Construction of Buildings. Construction of permanent buildings on top of landfilled areas
shall be prohibited during the operational phase except for buildings associated with landfill gas
recovery operations.
(34) Records for Operational and Plan Execution.
(a) The operator shall maintain a daily log to record operational information, including but
not limited to the type and quantity of solid waste received and the status of all
environmental control or monitoring systems.
(b) The operator of existing or new landfills receiving 100 tons or more per day shall weigh
all incoming solid waste.
(c) Operators of landfills that receive less than 100 tons per day shall, on a daily basis,
estimate the total weight and volume of waste delivered based upon the capacity of the
vehicles which delivered solid waste to the facility.
(d) The operator shall submit to the Department, no later than February 15 of each calendar
th
year, an annual report summarizing the facility's operations for the previous calendar year or
portion of a calendar year that waste is handled at the facility. The report shall describe and
summarize:
1. the amount of solid waste handled during that year with the quantity reported in tons;
2. the filled capacity of the facility in cubic yards and the estimated density of the
landfilled solid waste;
3. the amount of capacity remaining in the landfill in cubic yards;
4. the volume of daily and intermediate cover material applied to the landfill during that
year;
5. all environmental monitoring and sampling data trends from ground water, surface
water and gas monitoring systems; and
6. a demonstration of how the landfill's operations during the year complied with the
provisions of the recycling and composting plan contained as part of the facility's solid
waste management permit.
(35) Inspections. The facility shall be inspected by a third-party inspector in accordance with
310 CMR 19.018.
(36) Re-circulation of Leachate. The Department may allow the re-circulation of leachate if it
is demonstrated to the Department that such a procedure will be conducted to achieve a
reasonable environmental goal and the operation will not compromise the integrity of the landfill,
including the liner and leachate collection systems, or result in unacceptable adverse impacts to
the public health, safety or the environment, or result in nuisance conditions. A request for
leachate re-circulation shall include:
(a) the goals and expectations of the re-circulation activity;
(b) a report detailing the engineering considerations that need to be addressed by the re-
circulation activity including, but not limited to, stability of the landfill, leachate collection
system performance, odor concerns and landfill gas issues (generation rate and controls, etc.);
(c) identification of potential adverse impacts (odors etc.) resulting from the re-circulation
activity and a contingency plan to address any potential adverse impacts should they occur;
(d) methods used to monitor the performance of the re-circulation operations to ensure they
are within safe operating parameters and achieving project goals;
(e) amount and rate of leachate to be recirculated, how leachate will be distributed, and
storage needs and methods; and,
(f) an evaluation of financial assurance mechanisms to ensure the availability of adequate
funds to address corrective actions that may result if there are problems with the re-
circulation system.
(37) End-of-life Mercury-added Products. Mercury-added products that are hazardous waste
pursuant to 310 CMR 30.000: Hazardous Waste shall be handled in accordance with 310 CMR
30.000: Hazardous Waste. Mercury-added products that are not hazardous waste shall be
handled in accordance with 310 CMR 76.05(2).