990 CMR 6.03
Schedule and Location
(1) First Briefing Session. The Department shall conduct at least one briefing session within 30 days of
publication of the Council's determination that a proposal is feasible and deserving of state assistance. If a site
is specified in the Notice of Intent this session shall be held in the host community. If more than one site is
specified within the host community, the Department may consolidate the briefing sessions if such
consolidation will enhance public awareness and participation. If no site is designated in the Notice of Intent,
the Department, after consultation with the developer, shall determine the location of the initial briefing
session.
(2) Subsequent Briefing Sessions. Following the initial briefing session, the Department shall establish a
schedule with locations for briefing sessions which it deems appropriate and best calculated to insure public
awareness and participation in the siting process. If a developer has chosen to utilize the site suggestion process
pursuant to 990 CMR 7.00, within 30 days of the publication of the final suggested site list the Department
shall conduct at least one briefing session in each community on said final list.