205 CMR 135.02
Project Schedules and Reporting
(1) The commission may create guidelines under 205 CMR 135.00 to aid the commission in
its review and monitoring of the project. Such guidelines will be shared with the licensee and
may be amended as necessary by the commission.
(2) The commission shall, in accordance with M.G.L. c. 23K, §§ 10 and 11 approve for each
gaming licensee, a project schedule for the gaming licensee's capital investment in its gaming
establishment and related infrastructure which includes:
(a) all major stages of design and construction; including all permitting and approvals,
design deliverables, site preparation, foundation, structure, plumbing, electrical, mechanical,
exterior finish and fenestration, long lead items, insulation, interior finish and furnishings
and landscaping, building commissioning and commissioning of gaming equipment and
information technology systems.
Mass. Register #1375 10/5/18
(b) For a Category 1 gaming establishment, a timeline for commencement of the final stage
of construction pursuant to M.G.L. c. 23K, § l0(a); and
(c) a timeline for the stage of construction at which the gaming licensee shall be approved
to open for business or operate a slot machine pursuant to M.G.L. c. 23K, §§ 10(c) and 11(a).
(3) Within the time frame provided in the award of the gaming license, the licensee shall
provide to the commission for commission approval an affirmative action program of equal
opportunity whereby the licensee establishes specific goals for the utilization of minorities,
women and veterans on construction jobs and for contracting with minority, women or veteran
owned businesses during either design or construction; provided, however that such goals shall
be equal to or greater than the goals contained in Executive Office of Administration and Finance
Administrative Bulletin Number 14.
(4) If unforeseen and/or changed circumstances necessitate a change to a project schedule
approved pursuant to 205 CMR 135.02(2) which will impact the completion date or requires a
major change in the method or progress of construction, the gaming licensee may submit to the
commission for its approval a revised project schedule, with a detailed statement of the
unforeseen changed circumstances which justifythe revised project schedule. If the commission
approves such revised project schedule, it shall substitute and supersede the previously approved
project schedule.
(5) To ensure adherence to the project schedule approved pursuant to 205 CMR 135.02(2) or
(4), the gaming licensee shall submit to the commission in a media, format and level of detail
acceptable to the commission, quarterly a status report including:
(a) the total estimated cost of construction of the project and related infrastructure
improvements, including a sworn certification regarding costs incurred pursuant to 205 CMR
122.03: Costs Included in the Calculation of Capital Investment, and separately identifying
detailed costs for design, land acquisition, site preparation and construction and off-site
improvements;
(b) a sworn certification regarding the capitalization of the gaming licensee, sufficient for
the commission to determine, pursuant to M.G.L. c. 23K, § 10(e) or 11(c), that the gaming
licensee has adequate funds to complete the gaming establishment and related infrastructure
improvements;
(c) a copy of all design and construction contracts executed within the prior quarter by the
gaming licensee to design and construct the gaming establishment and related infrastructure
improvements;
(d) a status report reflecting the progress of construction and certifying compliance with the
approved project schedule for major stages of construction. In the event that the progress of
construction does not comply with the project schedule approved pursuant to 205 CMR
135.02, the licensee shall submit a detailed plan to bring the progress of construction into
compliance with the approved project schedule or submit a request for a revised project
schedule pursuant to 205 CMR 135.02(4); and
(e) a detailed statistical report pursuant to M.G.L. c. 23K, § 21(a)(23) on the number, gender
and race, and veteran status of individuals by job classifications hired to perform labor as part
of the construction of the gaming establishment and related infrastructure, and a comparison
of this report with the goals established by the gaming licensee and commission pursuant to
M.G.L. c. 23K, § 2l(a)(22). In the event the hiring of the aforementioned persons does not
comply with the goals established, the licensee shall submit within 20 days of a request by
the commission a response as to why the goals have not been achieved, identify any good
faith efforts that have been undertaken to achieve those goals and provide a plan to bring the
hiring into compliance with the goals.
(f) a report describing the number of contracts, total dollar amounts contracted with and
actually paid to minority business enterprises, women business enterprises and veteran
business enterprises for design and construction of the gaming establishment and related
infrastructure, and the total number and value of all subcontracts awarded to a minority,
women and veteran owned business, and a comparison of these reports with the goals
established by the gaming licensee and commission pursuant to M.G.L. c. 23K, § 21(a)(2l).
In the event the licensee's hiring of the aforementioned entities does not comply with the
goals established the licensee shall submit within 20 days of a request by the commission a
response as to why the goals have not been achieved, identify any good faith efforts that have
been undertaken to achieve those goals and provide a plan to bring the the dollar amount
contracted and spent into compliance with the goals.
(6) The licensee shall have a continuing obligation, pursuant to 205 CMR 120.01(2) to timely
provide to the commission an updated permits chart and all documents and information listed
in 205 CMR 120.01: Permitting Requirements, as well as any updates to the MEP A process
such that the commission is continuously apprised of all material developments with respect to
all permits and approvals required for the gaming establishment. Pursuant to 205 CMR
120.01(1)(h) the licensee shall provide to the commission copies of any appeal within 20 days
of filing, whether to a municipal or state entity or for judicial review, filed with respect to any
permit of approva1listed in 205 CMR 120.01(1) along with a copy of the docket sheet and each
decision on any appeal.
(7) In furtherance of specific goals for the utilization of minorities, women and veterans on
construction jobs, the licensee shall send and provide a copy to the commission, to each labor
union or representative of workers with which the licensee has a collective bargaining agreement
or other contract or understanding, a notice advising the labor union or workers representative
of the licensee's commitments pursuant to M.G.L. c. 23K § (15) and §§ 21(a)(21) and (22).
(8) Prior to the gaming establishment opening for business, in furtherance of specific goals for
the utilization of minority business enterprises, women business enterprises and veteran business
enterprises as vendors in the provision of goods and services to the gaming establishment, the
licensee shall provide to the commission an affirmative marketing plan in which the licensee
identifies specific goals, expressed as an overall program goal applicable to the total dollar value
of contracts entered into, for the utilization of minority business enterprises, women business
enterprises and veteran business enterprises to participate as vendors in the provision of goods
and services procured by the gaming establishment and any businesses operated as part of the
gaming establishment; provided, however, that the specific goals for the utilization of such
minority business enterprises, women business enterprises and veteran business enterprises shall
be based on the availability of such minority business enterprises, women business enterprises
and veteran business enterprises engaged in the type of work to be contracted by the gaming
licensee.
135.03 Design Review Process
(1) The commission or its representative may participate in the design review process for the
design of the project. This process may run in parallel to the local, state and federal review
process and may include all elements of the project, including but not limited to the gaming
establishment and any amenities approved by the commission, whether constructed together or
in phases, as well as any off-site improvements. The commission may participate in the
following key milestones of the design review process:
(a) development of initial concept;
(b) development of the schematic design;
©) completion of the final site plan and architectural design; and
(d) development of the construction design package.
(2) As part of the development of the initial concept, the commission may request a narrative
describing the project and stipulating the basis for the design. The narrative should include a
pictorial representation of the project design concept and a narrative description of the project.
(3) When the licensee has completed the schematic design phase, the commission may request
that the licensee submit the schematic design to the commission or its representative for review.
Such schematic design may include descriptions of the external facade of any structures that are
part of the project, all the major systems, a floor plan and any off site infrastructure
improvements planned by licensee. The commission or its representative may request, where
available, examples of materials to be used in the building facade,
(4) The commission or its representative may request for review and approval the final site plan
and architectural design package. Such final design package shall be in the form ready for
licensee's use in creating construction bid packages. Where available, the commission or its
representative may request examples of materials to be used on the exterior or in the interior of
the project as well as examples of the furniture and fixtures to be used in the project.
(5) The commission's representative may request construction packages for review prior to
putting such construction packages out for bid.