205 CMR 135.04
Inspection of Construction and Related Records
(1) At all times the commission or its representative may pbysically inspect the progress of
construction, subject to reasonable construction site safety rules, to determine the gaming
licensee's compliance with the approved design, project schedule, the terms and conditions of
the license, M.G.L. c. 23K, or 205 CMR
(2) The commission may request or have access to, at any time, plans, specifications,
submittals, contracts, financing documents or other records concerning the construction of the
project or related infrastructure. The licensee shall provide the requested materials to the
commission or its representative within ten days of the commission's request for such documents.
(3) Following an inspection of construction pursuant to 205 CMR 135.04(1) or review of
records pursuant to 205 CMR 135.04(2), the commission or its representative may notify the
gaming licensee of any non-compliance with the terms ofthe license, including non-compliance
with an approved design or project schedule pursuant to 205 CMR l35.02(2) or (4). Upon receipt
of such notification, the gaming licensee shall present a plan to the commission to address such
non-compliance to the satisfaction of the commission.