205 CMR 135.05
Certification of Final Stage of Construction: Category 1 Gaming Establishments
(1) Pursuant to M.G.L. c. 23K, § 10(a), the gaming licensee shall certify to the commission that
it bas reached the final stage of construction as described in the approved project schedule
pursuant to 205 CMR l3 5.02(2), or an approved revised project schedule pursuant to 205 CMR
l35.02(4).
(2) Upon receipt of such certification, the commission or its representative may inspect the
construction pursuant to 205 CMR 135.04(1), and request relevant plans, contracts, financing
documents or additional records pursuant to 205 CMR 135.04(2).
(3) If the commission approves the gaming licensee's certification pursuant to 205 CMR
135.05(1) that the gaming licensee bas reached the final stage of construction, it shall return to
the gaming licensee the deposit or release the deposit bond described in M.G.L. c. 23K, § 10(a),
and permit the gaming licensee to apply the deposit to the cost of the final stage of construction.
(4) If the commissionA disapproves the gaming licensee's certification pursuant to 205 CMR
135.05(1), the commission will notify the gaming licensee of the reasons for such disapproval,
and the gaming licensee shall proceed diligently to cure the reasons for the disapproval.