248 CMR 7.04
Initial Start-up and Final Adjustments
(1) For gas equipment with an input of one million BTU's or more per combustion chamber,
an authorized representative of the equipment or burner manufacturer shall perform the initial
start-up, final adjusting and testing of the burner and controls in the presence of the gas inspector.
Additionally, the serving gas supplier must be notified at least 48 hours in advance of the initial
startup to be given the opportunity to attend the startup.
(2)
Purging of Gas Equipment. The furnace, passes, and connected flue piping shall be
thoroughly purged before lighting of pilots or burners. This shall be done by creating air flow
through the setting by fully opening flue dampers and air shutters and by operation of induced
and forced draft fans, if present.
(3) Control Operating Tests.
(a) All controls shall be thoroughly checked for proper operation and sequencing before the
burner is put into operation. Manufacturer's instructions shall be followed.
(b) All safety shutoff gas valves shall be tested for gas tightness while in the closed position
before being placed in service. During this test, gas shall be shut off to all burners
downstream from the safety shutoff gas valve.
(4) Pilot Operation Tests.
(a) After the gas piping has been thoroughly cleared of air and any foreign materials, the
pilot burner shall be lighted and adjusted with the main burner manual and automatic valves
in the closed position. Adjustment to the pilot shall be made in accordance with
manufacturer's instructions.
(b) Pilots shall not deposit carbon when adjusted according to the manufacturer's
instructions.
(c) When escapement or bleed pilots are used, the discharge shall be in a fixed position and
shall be freely ignited by the continuous burning pilot or vented to a safe location.
(5) Burner Operation Tests.
(a) The main burner shall be put into operation and tested only after 248 CMR 7.04(2)
through (4) have been completed. Manufacturer's instructions shall be followed for light-off
and adjustment of the main burner.
(b) Pilots shall reliably effect immediate ignition of the main burner even when the gas
supply to the pilot(s) is reduced to a point where the pilot flame is just sufficient to actuate
or energize the flame detection device. Follow the manufacturer's instructions in conducting
this test.
(c) Continuously burning pilot flames shall not become extinguished: when the main
burners are turned on or off in a normal manner, either manually or by automatic controls,
when the air flow through the burner is rapidly changed from maximum to minimum or vice
versa after the main burners are shut off following operation of the equipment at its
maximum capacity, nor during any normal operating conditions that will occur. The above
tests shall be repeated three times.
(d) The pilot burner shall reliably ignite the main burner under any normal condition of
operation.
(e) The arrangement of burners, valves, and pilots shall be such that when only the pilots
supervised by the flame safeguard equipment are in operation, any burner or combination of
burners shall be effectively ignited without delayed ignition or flash back.
(f) Burner flames shall not flash back when fired at any rate within the installed operating
range of the burner.
(g) Burner flames shall not flash outside the equipment when the gas is turned on or off by
the automatic control mechanism.
(h) Proper air-gas ratio shall be maintained and combustion shall be complete over the full
installed operating range of the burner.
(6) Test for Venting. A check shall be made for proper venting with the burner operating at
maximum installed input and with all building exhaust fans operating which are in
communication with the room containing the equipment and with all outside closeable boiler
room openings shut.
(7) Instructions to the Operator.
(a) Complete written or printed instructions including wiring diagrams shall be supplied and
made conveniently available or posted in a permanent form in a prominent place near the
equipment. These instructions shall include complete start up as well as normal and
emergency shutdown procedures. Start up shall be from the methods provided by the control
system for that purpose.
(b)
To guard against malfunctioning all controls should periodically be tested on a
scheduled basis.
(c) Extended Shutdown. When equipment is shut down for an extended period it is
recommended that in addition to closing all gas valves, as a further precaution, gas be
prevented from leaking into the equipment by blocking off or disconnecting and capping or
plugging the gas supply pipe.