Rule 2357. (1) The supervisor of mineral wells shall prohibit the use of a drilling mud
pit if it is determined that the mud pit causes waste.
(2) Drill cuttings, muds, and fluids shall be confined by a pit, tank, or container which is
of proper size and construction and which is located as approved by the supervisor of
mineral wells or authorized representative of the supervisor of mineral wells.
(3) Only tanks shall be utilized while drilling a well that is located in an area zoned
residential before the effective date of these rules. The supervisor of mineral wells may
grant an exception if the applicant or permittee makes a request for an exception as part
of the written application for a permit. The supervisor of mineral wells may grant an
exception if an applicant or permittee satisfactorily demonstrates that a municipal water
system is utilized or required to be utilized.
(4) Drilling mud pits shall be located and plotted as instructed by the supervisor of
mineral wells. Before construction of the mud pit, a permittee shall demonstrate to the
supervisor of mineral wells or authorized representative of the supervisor of mineral
wells that there is not less than 4 feet of vertical isolation between the bottom of the pit
and the uppermost groundwater level. The bottom of the liner shall not be installed within
the observed groundwater level as determined while excavating the pit. If groundwater is
encountered during or before construction of the pit, then the permittee shall select 1 of
the following options and obtain the approval for the option from the supervisor of
mineral wells or authorized representative of the supervisor of mineral wells:
(a) The pit shall be designed and constructed so the bottom of the pit is not less than 4
feet above the groundwater level.
(b) The pit shall be designed and constructed so the bottom of the pit is above the
groundwater level, but less than 4 feet above the groundwater level. During encapsulation
the pit contents shall be solidified using a method approved by the supervisor of mineral
wells, except as provided in subrule (9) of this rule.
(c) The pit shall be relocated at the well site as approved by the supervisor of mineral
wells or authorized representative of the supervisor of mineral wells.
(d) Tanks shall be used, and drilling muds disposed of, at an approved off-site location.
(5) Drilling mud pits shall be constructed as instructed by the supervisor of mineral
wells and shall comply with both of the following minimum requirements:
(a) Pits shall be constructed with rounded corners and side slopes of not less than 20
degrees measured from the vertical.
(b) The bottom and sides of the pit shall be free of objects that could penetrate the liner.
(6) Drilling mud pits shall be lined as instructed by the supervisor of mineral wells and
shall comply with all of the following minimum requirements:
(a) Pits shall be lined with 20-mil virgin polyvinyl chloride liners as approved by the
supervisor of mineral wells or with other liners that meet or exceed the 20-mil virgin
polyvinyl chloride liner requirement.
(b) Ample liner material shall be installed in a manner to allow for sags and material
loading to reduce stress on the liner and allow for a minimum 11-foot flat apron on all
sides, including enough liner material to underlay the drilling mud tank, salt washer, and
shale shaker.
(c) The bottom of the lined pit shall be weighted with earthen material or water before
anchoring the ends of the liner on the surface or placing drilling muds in the pit.
(d) Ripping, tearing, puncturing, or other destruction of a liner that may cause loss of
fluids is prohibited.
(e) Liner field seams are prohibited, except for liner field seams that result from failures
in the liner due to abrasion or accidental perforation, which shall be immediately repaired
in the field using the manufacturer's recommended procedures.
(7) Drilling mud pits shall be utilized as instructed by the supervisor of mineral wells
and shall comply with all of the following minimum requirements:
(a) Solid salt cuttings shall not be released to in-ground drilling mud pits. Solid salt
cuttings obtained while drilling shall be collected in a container at the shale shaker and
either diverted to a device that will result in the dissolving of the solid salt cuttings and
the proper disposal of the resultant brine under R 299.2425 or removed from the drilling
site to a licensed disposal facility.
(b) Only the following may be placed in a lined pit:
(i) Water-based drilling muds generated or utilized while drilling with a fresh water
drilling fluid.
(ii) Drilling fluids generated or utilized while drilling with a fresh water drilling fluid.
(iii) Cuttings obtained while drilling with a fresh water drilling fluid.
(iv) Cuttings and the solid fraction of drilling muds generated or used while drilling with
other than a fresh water drilling fluid, other than drill cuttings prohibited by subdivision
(a) of this subrule, if the cuttings and the solid fraction of drilling muds do not contain
free liquids as determined by the United States Environmental Protection Agency, Paint
Filter Liquids Test, Method 9095, September 1986 Edition, which is adopted by
reference in these rules. Copies are available for inspection at the Lansing Office of the
Geological and Land Management Division of the Department of Environmental Quality.
Copies may be obtained without charge as of the time of adoption of these rules from the
Michigan Department of Environmental Quality, Geological and Land Management
Division, P.O. Box 30256, Lansing, Michigan 48909, or from the United States
Environmental Protection Agency, Office of Research and Development, 26 West Martin
Luther King Boulevard, Cincinnati, Ohio 45268. A permittee shall provide the necessary
equipment at the site of the drilling rig to perform the paint filter liquids test.
(v) Water-based drilling muds and entrained cuttings, other than drill cuttings prohibited
by subdivision (a) of this subrule, which are generated or utilized while drilling with
other than a fresh water drilling fluid, which contain weighting materials or lost
circulation materials, and which cannot reasonably be treated to eliminate free liquids as
determined by the paint filter liquids test identified in paragraph (iv) of this subdivision,
if approved by the supervisor of mineral wells or authorized representative of the
supervisor of mineral wells.
(vi) Native soils.
(vii) Cementing materials.
(viii) Stiffening or solidification materials approved by the supervisor of mineral wells.
(c) Machine oil, refuse, completion and test fluids, liquid hydrocarbons, or other
materials may not be placed in a pit.
(8) If a drilling mud pit is not closed immediately after reaching drilling completion,
then a permittee of a well shall fence the perimeter of the drilling mud pit as soon as
practical after drilling completion, but not later than 30 days after drilling completion, to
prevent public access.
(9) A permittee of a well shall close a drilling mud pit as instructed by the supervisor of
mineral wells and be in compliance with all of the following minimum requirements:
(a) All free liquids above the solids in the pit shall be removed to the maximum extent
practical and disposed of in an approved disposal well or used in a manner approved by
the supervisor of mineral wells.
(b) A permittee of a well shall, before encapsulation, test the fluids and cuttings
remaining in the pit to determine the concentrations of chloride and total petroleum
hydrocarbons and provide certification to the supervisor of mineral wells or authorized
representative of the supervisor of mineral wells of the test results, except that a permittee
is not required to test the fluids and cuttings remaining in the pit for chloride and total
petroleum hydrocarbons if the well was drilled with water from a source approved by the
supervisor of mineral wells and if, during the drilling operation, liquid hydrocarbons were
not encountered. If the testing reveals chloride concentrations in excess of 500 PPM or
total petroleum hydrocarbon concentrations in excess of 11,000 PPM, then the pit
contents shall be excavated and disposed of in a licensed disposal facility. The excavation
shall be filled with clean fill material, graded to original ground grade level and seeded.
(c) A drilling mud pit which is encapsulated shall comply with all the following
requirements:
(i) The pit shall be encapsulated and buried as soon as practical after drilling
completion, but not more than 6 months after drilling completion.
(ii) The contents shall be stiffened before encapsulation, except as provided in subrule
(4)(b) of this rule. Earthen materials shall be mixed with the pit contents to stiffen the pit
contents sufficiently to provide physical stability and support for the pit cover. An
alternative pit stiffening process approved by the supervisor of mineral wells may be used
at the option of a permittee or if required by the supervisor of mineral wells.
(iii) Apron edges of the liner shall be folded over the pit proper.
(iv) The drilling mud pit shall be totally covered with a separate piece of material that
meets or exceeds the specifications of a 20-mil virgin polyvinyl chloride cover as
approved by the supervisor of mineral wells. The cover shall extend beyond the outer
edges of the pit to cover and entirely encapsulate the pit and shall be sloped to provide
surface drainage away from the pit.
(11) The drilling mud pit shall be buried not less than 4 feet below the original ground
grade level.
(11) A test well that does not penetrate below the deepest fresh water aquifer shall
comply with both of the following requirements:
(a) Subrule 7(c) of this rule.
(b) Within 6 months following drilling completion, the drilling mud pit for a test well
that does not penetrate below the deepest fresh water aquifer shall be filled with clean fill
material or native materials and graded to original ground grade level.
(12) A test well that does not penetrate below the deepest fresh water aquifer is exempt
from all other provisions of this rule except subrule (11).