R 324.811
R 324.811 Loss of mechanical integrity.
Cite as Mich. Admin. Code R 324.811
Rule 811. (1) A permittee of an injection well shall notify the supervisor or authorized
representative of the supervisor of any pressure test failure, significant pressure changes,
or other evidence of a leak in an injection well, within 24 hours of the pressure test failure,
significant pressure changes, or other evidence of a leak. For other evidence of a leak
received via logging, the notification shall occur within five working days after the operator
first determines that the condition exists from reading the log data, but not later than 10
working days after the day the operator receives the log data. If there is evidence that
indicates an injection well is not, or may not be, directing the injected fluid into the
permitted injection interval, a permittee of an injection well shall immediately cease
injection.
(2) A permittee shall submit written notice of the pressure test failure, significant pressure
changes, or other evidence of a leak to the supervisor or authorized representative of the
supervisor within 5 days of the occurrence, or within 10 days of receiving well logging
data, on a form prescribed by the supervisor. If injection has ceased pursuant to subrule (1)
of this rule, then a permittee shall not resume injection until the permittee has tested or
repaired the well, or both. If the repair requires a change of well status pursuant to
R 324.511, or a permit modification, then a plan shall be submitted to, and approved by,
the supervisor or authorized representative of the supervisor. The repair or modification
plan must demonstrate protection of any underground sources of drinking water.
(3) Before resuming injection, a permittee must demonstrate the well has mechanical
integrity and receive an authorization to inject. Verbal authorization from the supervisor or
authorized representative of the supervisor is acceptable to commence injection. Written
authorization to inject from the supervisor or authorized representative will be issued
within 7 days of verbal authorization. Prior to issuance of an authorization to inject, the
supervisor or authorized representative shall have witnessed the test or received the test
data, reviewed the test data, and determined the permittee has demonstrated that the well
has mechanical integrity.