R 325.1665
R 325.1665 Plugging of dug wells and crock wells.
Cite as Mich. Admin. Code R 325.1665
Rule 165. A large diameter dug well or crock well shall be plugged pursuant to the
provisions of R 325.1663 and R 325.1664 or may be plugged as follows:
(a) A layer of bentonite chips or bentonite pellets that is not less than 6 inches thick shall
be placed at the bottom of the well. The remainder of the well shall be plugged by placing
clean soil backfill in
layers that are not more than 10 feet thick, with a layer of bentonite chips or bentonite
pellets that is not less than 6 inches thick placed on top of each clean soil backfill layer.
Dry granular bentonite may be used
in place of, or in combination with, bentonite chips or bentonite pellets, and neat cement
or concrete grout may be poured if the well has been dewatered before plugging.
(b) The uppermost section of concrete crock or tile or the upper 3 feet of stone, brick, or
other curbing material that supports the well bore shall be removed. Before backfilling the
well up to the ground surface, a layer of bentonite chips or bentonite pellets that is not less
than 6 inches thick shall be placed.