PURPOSE: This rule holds the amusement ride owner responsible for the cost of an inspection/investigation resulting from an accident falling within the purview of this Act. (1) The cost of an inspection/investigation as a direct result of an accident as defined in this Act shall be the responsibility of the amusement ride owner due upon completion of the inspection/investigation by the contracted inspector at a rate of one hundred twenty-five dollars ($125) per hour plus actual expenses. AUTHORITY: section 316.206, RSMo 2000.* Original rule filed March 1, 1999, effective Sept. 30, 1999. Amended: Filed April 2, 2003, effective Oct. 30, 2003. *Original authority: 316.206, RSMo 1997.