4 CSR 85-9.035
Support Contract
PURPOSE: The purpose of this rule is to
explain the requirements for a properly submitted support contract.
(1) The following will be included as part of
the support contract submission:
(A) The Support Contract Submission
Form, included herein; and
(B) A final executed copy of the support
contract.
(2) The department reserves the right to make
reasonable request for additional documentation in order to approve or deny a Support
Contract Submission Form.
(3) A project proposal must meet the following statutory criteria in order for the project
to be approved for tax credits:
(A) There must be cap space available. If
your project was given a reservation of tax
credits at the project proposal stage, you will
already have cap space allocated to your sporting event and department will review your
support contract for statutory compliance;
(B) You can submit a project proposal along
with a support contract submission;
(C) If the program cap has been reached,
and your support contract submission would
have been otherwise approved, your sporting
event will be placed on administrative hold
until the earlier of—
1. A date upon which there is cap space
available due to other denials in the fiscal year
covered by the application, at which point cap
space will be reserved for the applicant; or
2. Until a date ninety (90) days following
the end of the sporting event, at which point
the project will be denied;
(D) A project will be denied, even if it had
been previously approved, when it becomes
apparent that the sporting event will not be
held as indicated in the support contract.
Denied projects shall have their reserved cap
space allotted to other sporting events;
(E) The applicant and site selection organizations must be valid and fit within the
appropriate definitions provided under 4 CSR
85-9.011;
(F) No site for a sporting event may have
been chosen prior to December 1, 2012, and
no support contract will be approved after
August 28, 2019; and
(G) No support contract will be certified
unless the site selection organization has chosen to use a location in Missouri during a
competitive bidding process in which at least
one (1) competitive bid came from out of
state.
Community Services
Community Services
AUTHORITY: section 67.3000, RSMo Supp.
2013.* Emergency rule filed April 1, 2014,
effective April 11, 2014, expired July 30,
2014. Original rule filed Feb. 7, 2014, effective July 30, 2014.
*Original authority: 67.3000, RSMo 2013.