7 CSR 10-24.100
Selection Procedures and Award Criteria
PURPOSE: This rule provides the criteria
used to determine whether standard designbuild or modified design-build procedures
will be used.
(1) The commission will use a two- (2-)
phase selection procedure for all design-build
projects. If it is determined by the commission that the design-build procedure is not
appropriate for a given project, based on the
criteria in 7 CSR 10-24.130, the modified
design-build contracting method may be utilized.
(2) The following criteria will be used to
decide whether design-build or modified
design-build selection procedures are appropriate:
(A) The number of offers anticipated;
(B) Proposers are expected to perform substantial design work before developing price
proposals;
(C) Proposers will incur a substantial
expense in preparing proposals; and
(D) Commission has sufficiently defined
and analyzed other contributing factors,
including:
1. The requirements of the project;
2. The time constraints for delivery of
the project;
3. The capability and experience of
potential contractors;
4. Commission capabilities to manage
the standard design-build selection process;
and
5. Any other criteria that the commission may consider appropriate.
(3) The commission will identify the selection procedure and award criteria in the
Request for Qualification (RFQ). The following will determine the type of selection procedure and award criteria used by the commission:
(4) Commission will base the source selection decision on a comparative assessment of
proposals against all selection criteria in the
solicitation. Commission may use reports and
analyses prepared by others, however, the
source selection decision represents the commissionโs independent judgment.
(5) The source selection decision will be documented, and the documentation will include
the rationale for any business judgments and
tradeoffs made or relied on, including benefits
associated with additional costs. Although the
rationale for the selection decision is documented, that documentation need not quantify
the tradeoffs that led to the decision.
(6) A minimum of two (2) to a maximum of
five (5) firms will be short-listed. If the commission fails to receive offers from at least
two (2) responsive proposers, the offers will
not be opened; and the commission may readvertise the project.
AUTHORITY: sections 226.020, 226.030,
and 227.107, RSMo 2016.* Original rule
filed Aug. 15, 2005, effective Feb. 28, 2006.
Amended: Filed Dec. 5, 2017, effective July
30, 2018.
*Original authority: 226.020, RSMo 1939; 226.030,
RSMo 1939, amended 1965, 2003, 2004, 2009; and
227.107, RSMo 2002, 2007, 2009, 2011, 2016.